The First Successful Short-Radius Re-Entry Well in Deep Gas Drilling in Saudi Arabia

机译:沙特阿拉伯深气钻的第一个成功的短半径重新进入

获取原文

摘要

This paper discusses the planning and execution of the first successful short-radius sidetrack in deep gas drilling in Saudi Arabia. ANDR-XYZ was sidetracked from vertical at 12,242 ft and built inclination to 90° with maximum dog leg severity recorded as 39°/100 ft. Thereafter, a 2,400 ft lateral was drilled in the Khuff-B reservoir. Total depth was revised because of deteriorating reservoir quality. The operating time was 53 days versus 60 days planned. The short-radius sidetrack was one of three options (option 3, below): 1. Sidetracking in the 9 5/8-in. casing set in the Khuff formation. Apart from cost reasons, this option was discarded because of high Jilh pressure requiring the mud weight to be increased from 102 pcf to 152 pcf, which would create well control and directional drilling difficulties. 2. Milling the 7-in. liner, drilling a new 8 3/8-in. hole, setting a new 7-in. liner, and then drilling a 5 7/8-in. hole across the reservoir. Apart from being time consuming and costly, this option did not reduce technical complexity since it might have exposed the 9 5/8-in. casing across the liner lap. The condition of this section could not be guaranteed because of a previous milling operation while drilling the original wellbore. 3. Re-entering the well by sidetracking in the 7-in. liner below the 9 5/8-in. casing. This required drilling a short- radius curve in the 5 7/8-in. section and continuing drilling and geosteering the well through the reservoir. Such a high buildup rate had never been successfully achieved before at this sidetrack depth in the Khuff reservoirs in Saudi Arabia. Several technical considerations were taken into account including the depth and type of whipstock, the length of rathole, design and analysis of the sidetrack bottomhole assembly (BHA) including torque and drag analysis, as well as overall operations strategy to achieve the well objectives. Several challenges were overcome and lessons were learned, which will be detailed in this paper. The successful delivery of this well resulted in saving of 45 rig days compared to the other options. The well also extended the frontier of drilling and workover options and opened up avenues to reenter several wells in deep gas drilling in Saudi Arabia.
机译:本文讨论了沙特阿拉伯深气钻的第一个成功的短半径侧面的规划和执行。 andr-xyz以12,242英尺的垂直侧面,并建造倾斜度至90°,最大狗腿严重程度记录为39°/ 100英尺。此后,在Khuff-B储库中钻出2,400英尺的横向。由于储层质量恶化,因此修改了总深度。操作时间为53天,而60天计划。短半径Sidetrack是三种选项之一(下面的选项3):1。在9 5/8英寸中侧面。套管在Khuff组中设置。除了成本原因之外,由于高JILH压力要求泥浆重量从102个PCF增加到152个PCF,因此丢弃了这种选择,这将产生良好的控制和定向钻井困难。 2.铣削7英寸。衬垫,钻出新的8 3/8英寸。洞,设置一个新的7-in。衬垫,然后钻5 7/8英寸。水库的洞。除了耗时和昂贵的昂贵,此选项不会降低技术复杂性,因为它可能会暴露9个5/8英寸。整个衬垫膝盖上的套管。由于钻井原始井筒的同时,因此不能保证本节的状况。 3.通过在7英寸的侧面重新进入井。衬垫下方9 5/8英寸。套管。这需要钻出5 7/8英寸的短半径曲线。部分和持续钻井和通过水库井下钻孔。在沙特阿拉伯的Khuff水库的这种侧面侧面之前从未成功地实现了这种高积累率。考虑了几种技术考虑因素,包括扭锁的深度和类型,Roorlole的长度,侧面的底座组件(BHA)的设计和分析包括扭矩和拖曳分析,以及实现井目标的整体运营策略。克服了几个挑战,学到了课程,这篇论文将详述。与其他选项相比,这一良好的成功交付使得节省了45天。该井还延长了钻井和工作台的前沿,并打开了在沙特阿拉伯深海钻井中重新进入几个井。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号