A different way of bidding for contract work is introduced and discussed in this paper. The bid is priced on a per iteration basis. The throughput goal of each iteration is estimated in story point format based on projected load factor, planned work days, and staff plan. The development team is responsible for achieving the target throughput goal of each iteration. Though pricing bid this way gains client trust quickly, key lesions are learnt and advice are given specifically on estimation, load factor projection, and client education.
机译:在本文中介绍并讨论了合同工作的不同竞标方式。竞标以迭代的价格为基础。根据预计的负载因子,计划工作日和员工计划,每次迭代的吞吐量目标估计。开发团队负责实现每次迭代的目标吞吐量目标。虽然以这种方式竞标此方法很快获益客户信任,但学习了关键病变,并专门针对估计,负载因子投影和客户教育提供建议。