OPTIMIZATION OF REFRACTORY LINING DESIGN AND INSTALLATION PRACTICE TO REDUCE VESSEL DOWNTIME AND MAXIMIZE PERFORMANCE OF ANODE REFINING VESSELS

机译:优化耐火衬里设计和安装实践,以降低船舶停机和最大化阳极炼油容器的性能

获取原文

摘要

Anode vessels are often relined with refractory every one to two years and a typical reline time can take between 16-20 days. Modern refractory designs using dense, corrosion resistant brick applied directly to the vessel shell in the high wear areas around and above the tuyeres and at the slagline can yield a lining life of up to 4-5 years before a complete reline is necessary. Installation methods using brick delivery on roller conveyors through an endwall access port and complete anchoring of the brick to allow for lining self-support can take days off the installation time. It is possible, therefore, to reduce the refractory relining period by 50 percent and increase lining life by 100 percent compared to typical anode repair schemes.
机译:阳极容器通常用每一到两年的难治性,典型的Reline时间可能需要16-20天。现代耐火材料设计使用致密,耐腐蚀砖直接施加到大型磨损区域,在甲状腺肿和上方的高磨损区域,并且在斯拉格线上可以在完整的Reline之前产生长达4-5年的衬里寿命。通过端墙接入口使用滚筒输送机上的砖块送料的安装方法,并完成砖块的锚固以允许衬里自我支持可能需要数天的安装时间。因此,与典型的阳极修复方案相比,可以将耐火电流的耐火电流降低50%并提高衬里寿命100%。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号