首页> 外文会议>Natural Gas Technologies Annual Conference and Exhibition >FAST TRACKED REMEDIAL DESIGN AND REMEDIAL CONSTRUCTION AT A FORMER MANUFACTURED GAS PLANT SITE
【24h】

FAST TRACKED REMEDIAL DESIGN AND REMEDIAL CONSTRUCTION AT A FORMER MANUFACTURED GAS PLANT SITE

机译:以前制造的煤气厂现场快速跟踪的补救设计和补救施工

获取原文

摘要

This paper summarizes a 'fast-tracked' remedial design and construction project at a former manufactured gas plant (MGP) site located in Pennsylvania. The project was located on a portion of the 1,000th site redeveloped under the Pennsylvania Land Recycling Program, where President George W. Bush signed legislation to assist developers in cleaning up brownfields in 2002. During 2004, PECO (a regional gas and electric provider) approached the owner of the property about performing environmental investigation and potential follow-up on remedial activities at this former MGP site (about 1 acre in size), which operated from 1875 to 1917 (Figure 1). The goal of this cleanup activity was threefold: (1) remediate this site as part of this utility's strong commitment to cleaning up former MGP sites that were inherited from its predecessor companies, (2) obtain environmental site closure from the state regulatory agency, and (3) complete remedial activities before the property owner began construction of a residential building complex at the site. A critical element of this remedial project was that the property owner had a tight schedule to construct this complex. Therefore, PECO (and its subcontractors) needed to quickly obtain subsurface information, develop a remedial design, and finish remedial construction within this tight schedule. Following negotiation of an access agreement between PECO and the Site property owner, URS Corporation (URS) performed an expedited site investigation to characterize soil and groundwater quality and to develop a plan for remedial action. Site characterization activities included the completion of a geophysical investigation, soil borings, test pits, and installation of groundwater monitoring wells. Based on the findings of the Site characterization, a remedial design was developed that involved: (1) removal and storage of the overburden soils within the 1-acre site footprint, (2) advancement of 760 linear feet of steel sheet pile, (3) dewatering the excavation, (4) moisture-conditioning of MGP impacted soils and (5) developing a groundwater treatment system that would meet the Publicly Owned Treatment Work's (POTW) specifications. The time from initial investigation to initiation of the remedial activities at the Site was a period of 11 months. During the 11 months that led up to the remedial action at the Site, the Remedial Action Work Plan (RAWP) was completed, remedial contract bid documents were prepared and a remedial contractor was selected. The successful partnership established between URS and the selected remediation contractor allowed for the expedited cleanup of the Site. The contractor selected for the remedial work was Enviro-Air Technologies, Incorporated, a small woman-owned business enterprise. Due to the size of the remediation contractor's company, and the capital expenditure for the project, cash flow for the remediation contractor was extremely important during the duration of the project. Therefore, PECO, URS and the remediation contractor developed a mutually agreeable arrangement that would allow a savings of 2% of each invoice paid within 20-days. This allowed for invoicing every ten working days and payment to the remediation contractor every 20-days for a savings of approximately $60,000 during the duration of the project. The length of the remedial construction project was 4 months, which resulted in the removal of 17,000 tons of MGP-impacted soils, treatment and discharge of 4,000,000 gallons of water to the POTW, and re-use of overburden soils. The area of excavation and shoring is presented on Figure 2. The project activities were completed on schedule with particular attention paid to safety and without incident.
机译:本文总结了位于宾夕法尼亚州的前制造的天然气植物(MGP)遗址的“快速跟踪”的补救设计和建筑项目。该项目位于宾夕法尼亚州土地回收计划下的1,000个地点的一部分,乔治·W·布什总统签署了立法,以协助开发商在2002年清理棕色地区。2004年,PECO(区域天然气和电力提供者)接近该物业的所有者关于在本前MGP网站(大约1英亩的规模)上进行环境调查和潜在的后续行动,该活动从1875年到1917年运营(图1)。这种清理活动的目标是三倍:(1)将本网站补救,作为本效果的一部分,致力于清理从其前任公司继承的前MGP网站,(2)从国家监管机构获取环境网站关闭,以及(3)在物业所有者开始在该网站开始建设住宅楼综合体建设之前完成补救活动。该补救项目的一个关键要素是,业主有一个紧张的时间表来构建这一复杂。因此,PECO(及其分包商)需要快速获取地下信息,在此紧密的时间表内开发补救设计,并完成修复结构。在谈判PECO与网站物业所有者之间的访问协议之后,URS Corporation(URS)执行了一项快速的网站调查,以表征土壤和地下水质量,并制定一个补救行动计划。现场表征活动包括完成地球物理调查,土壤钻孔,测试坑和地下水监测井的安装。基于现场表征的调查结果,开发了一种补救设计,涉及的:(1)在1英亩的位点占地面积内去除和储存覆盖的土壤,(2)钢板桩760线脚的进步(3 )脱水挖掘,(4)MGP撞击土壤的湿度调节和(5)开发地下水处理系统,符合公有制的处理工作(POTW)规格。从初步调查开始启动该网站的补救活动的时间是11个月。在11个月内导致本网站的补救行动,补救措施工作计划(RAWP)已完成,编制补救税授权文件,选定了补救承包商。在URS和所选修补程序之间建立的成功伙伴关系允许加急清理本网站。为补救工作所选的承包商是Enviro-Air Technologies,一个小型女性商业企业。由于补救承包商公司的规模,以及该项目的资本支出,修复承包商的现金流在项目期间非常重要。因此,PECO,URS和补救承包商制定了一种可靠的安排,允许节省2%的每份发票在20天内支付。这允许每隔十天的工作日发出每20个工作日和支付每20天的补救承包商,以节省约60,000美元。补救建设项目的长度为4个月,导致去除17,000吨的MGP抗冲击土壤,治疗和排放4,000,000加仑水,并重新使用覆盖度土壤。挖掘和支撑面积如图2所示。项目活动按计划完成,特别注意安全和毫无事件。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号