首页> 外文会议>Iron and Steel Technology Conference >Highly Productive, Reliable and Unique Casting at Badische Stahlwerke
【24h】

Highly Productive, Reliable and Unique Casting at Badische Stahlwerke

机译:Badische Stahlwerke的高效性,可靠和独特的铸造

获取原文

摘要

The two 100% scrap based electric arc furnaces at Badische Stahlwerke currently have a furnace output of 8,559 tgb/d with an average of 116.7 tons tap weight per furnace and an operating time of 305.4 days. The tap-to-tap time of 39.28 min at a power-off time of 9.8 min and an average delay time of 1.91 min/heat, along with the 11 strands of two continuous casting machines present a challenge. An annual output of 2,614,095 tons means 231,500 tons of casted steel per strand. In recent years, attempts have been made with section size extensions, with experiments of up to 8(1/4) inch being successfully carried out on a casting radius of 20.3 feet. The steel plant offers two production lines, consisting of a furnace, a ladle furnace and a continuous casting machine. Continuous improvements have also resulted in an asymmetric casting performance. CCM 2, offers 6 strands with a maximum casting capacity of 231.5 t/h. The CCM 1 on line 1 has 5 strands and reaches a max. casting speed of 170 t/h. For organizational reasons, the billets 6(1/4) inch are produced exclusively on CCM 1. To compensate this casting asymmetry, some heats of line 1 are casted on the CCM 2. This results in a forward planning of the respective heats, especially with different steel grades on both furnaces. Up to two heats are in a buffer position on CCM 2 therefore a precise control of the tap temperature and the cooling rate of the heats is crucial. The delay time on the furnaces waiting for the CCMs was reduced from 134.1 h in 2015 to 80.2 h in 2016. In order to minimize delays on all units, a preventive weekly maintenance takes place every Thursday. Several re-stranding simulations for the function check of all components end the preventive maintenance for the casters. Typical wear components were significantly optimized with regard to installation, removal and work force. The cooling chambers of cooling zone 2 are physically separated from one another to enable a breakthrough cleaning while other strands are in production. Up to 90 heats can be operated on a 5-strand tundish for CCM 1. This equates to 2,100 tons on the tundish nozzle, on the 6-strand tundish for CCM 2 this value is reached at 110 heats but also values of 115 heats are possible. Both continuous casting machines have to change the tundish twice until the next scheduled maintenance day. Tundish changes are made via the casting crane and require between 30 and 45 min. Both CCMs also allow the tundish to tilt in the system and a tundish is deslagged every 8 hours. The ladles are not brought into the casting position with a ladle turret, but this is done via a ladle car. This is a very quick change of a ladle, in less than 90 seconds from the closing gates of the ladles until opening. Furthermore this principle offers more safety to the ladle change. No ladle tundish shroud is used and the flying nozzle changer can be used up to 6 sliding blocks per strand. Due to the open stream for mold lubrication rape seed oil is used. The oil consumption is 0.15 qt/tgb. A specificity is that there are no guides, rolls or plates, below the mold. Despite the lack of foot rolls the breakthrough rate has been reduced from 2.3% in 2015 to 0.1% in 2016. Regarding rhomboidity, diagonal differences of an average of 0.15" (4 mm) are currently achieved with minimal bulging. Malfunctions in the rolling mill caused by billet defects are at 249 minutes for the year 2016 within total of 4 events. For primary cooling, BSW relies on spray mold technology. With regard to the life span of the mold tube, 800 - 1,000 heats per mold tube are possible, which corresponds to up to 18,740 tons of casted steel. Mold tubes close to the end of life time are used exclusively on the CCM 2. This caster has retractable oscillation tables and the molds can be exchanged during casting. In principle, mold tubes are not repaired and returned to the manufacturer after use. A team of one-first and three-second casters per shift are needed for a CC
机译:Badische Stahlwerke的两种100%废钢电弧炉目前具有8,559吨TGB / D的炉材输出,平均每炉扣重量为116.7吨,操作时间为305.4天。在9.8分钟的电源关闭时间和1.91分钟/热量/加热的平均延迟时间,连续两个连续铸造机器的电源关闭时间为39.28分钟,呈现出挑战。年产2,614,095吨,每股铸钢231,500吨。近年来,尝试已经采用截面尺寸扩展,实验高达8(1/4)英寸,铸造半径为20.3英尺。钢铁厂提供两条生产线,由炉子,钢包炉和连续铸造机组成。持续改进也导致了不对称的铸造性能。 CCM 2,提供6个股线,最大铸造能力为231.5吨/小时。第1行上的CCM 1具有5个股线并达到最大值。铸造速度为170吨/小时。对于组织原因,6(1/4)英寸产生只在CCM 1.钢坯为了补偿该铸造不对称,线1的一些加热被浇注在CCM 2.这导致在相应的加热的正向规划,特别是在两个炉子上用不同的钢等级。在CCM 2上的缓冲位置处最多两个加热因此,拍摄温度的精确控制和热量的冷却速率至关重要。等待CCMS的炉子上的延迟时间从2015年的134.1小时降至2016年80.2小时。为了最大限度地减少所有单位的延误,每周四都会发生预防性每周维护。所有组件功能检查的几种重新划分模拟结束了脚轮的预防性维护。在安装,移除和效力方面,显着优化了典型的磨损组分。冷却区2的冷却室彼此物理地分离,以实现突破性清洁,而其他股线在生产中。高达90个加热可以在5链中间包被操作为CCM 1.这等同于在中间包水口2100吨,在6链中间包为CCM 2在110个加热达到该值也是115个加热值是可能的。连续铸造机器都必须两次改变中间包,直到下一个预定的维护日。中间包通过铸造起重机进行,需要30至45分钟。两个CCMS还允许中间包在系统中倾斜,并将中间包每8小时倾斜。钢包不会用钢包炮塔进入铸造位置,但这是通过钢包汽车完成的。这是钢包的非常快速的变化,距离钢包的关闭门不到90秒,直到打开。此外,这个原则对钢包变化提供了更多的安全性。没有使用钢包中间罩,并且每股飞行喷嘴换流器最多可使用6个滑动块。由于液体润滑的开放流,使用了油菜籽油。油耗为0.15 QT / TGB。特异性在于模具下方没有导向器,卷或板。尽管缺乏脚轧率突破率从2015年的2.3%降低到2016年的0.1%。关于菱形,平均凸出的对角线差异为0.15“(4毫米),并且具有最小的凸出。轧机中的故障2016年雪间缺陷引起的总共249分钟,共计4个事件。对于初级冷却,BSW依赖于喷雾模具技术。关于模具管的寿命,每个模板的800-10次加热是可能的,这对应于高达18,740吨的铸钢。靠近终生末端的模具管专门用于CCM 2.该脚轮具有可伸缩的振荡桌,并且模具可以在铸造期间更换。原则上,模具管不是使用后修复并返回制造商。CC需要每次班次的一级和三秒脚轮的团队

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号