Recommendation of site commissioning tests for rapid recovery transformers with an installation time less than 30 hours

机译:现场调试测试的建议,用于快速恢复变压器,安装时间不到30小时

获取原文

摘要

Transformer testing is an indispensable procedure to guarantee that transformers are fulfilling all requirements and guaranteed values. After completed FAT (Factory Acceptance Test), to proof the transformer design, site commissioning test shall be performed to detect potential transport damages or faults at site installation before energizing the transformer. As a minimum requirement, we recommend to perform a dissipation factor (tanδ)-, TTR (Transformer Turns Ratio)-, insulation resistance-, ohmic resistance and SFRA (Sweep Frequency Response Analysis) measurement for conventional transformers as site tests. Depending on circumstances, various additional tests can be performed according to customer requirements. For transformer or reactor site works, the installation time might be critical (e.g. outage time of a power plant) but can be planned in advance. In case of an emergency, the time between failure and energizing the replacement unit is crucial. But also under time pressure, to dispense on site test is saving on the wrong place, and may lead to huge technical damages and monetary losses. A different approach to overcome a long installation and commissioning time are multi ratio and lightweight single phase transformers filled with environmental friendly synthetic ester, which can be transported without any special transport permits. This has also been proven at a demonstration run where it took just 30 working hours within three working days, to install, test and energize a 345 kV transformer bank, three 1-phase units each 100 MVA, which worked then in regular network operation including overload conditions. We give some recommendation about the required site tests, due to the fact that these transformers are more complex compared to conventional transformers. The higher complexity is justified by the fact that the resilience transformers are covering many different transformer designs and can be installed very flexible in the shortest possible time on site.
机译:变压器测试是一种不可或缺的程序,可以保证变换器符合所有要求和保证值。完成脂肪(工厂验收测试)后,验证变压器设计,应在激励变压器之前检测现场安装的潜在运输损坏或故障的现场调试测试。作为最低要求,我们建议使用传统变压器的耗散因子(TANδ) - ,TTR(变压器匝数比) - ,绝缘电阻,欧姆电阻和SFRA(扫描频率响应分析)作为现场测试。根据情况,可以根据客户要求执行各种额外的测试。对于变压器或反应堆部位,安装时间可能是至关重要的(例如,发电厂的停电时间),但可以提前计划。在紧急情况下,失效和激励替换单元之间的时间至关重要。但也在时间压力下,分配在现场测试上是节省错误的地方,可能导致巨大的技术损害和货币损失。克服长安装和调试时间的不同方法是填充有环保合成酯的多重比和轻量级单相变压器,可以在没有任何特殊运输许可的情况下运输。这也已被证明在一个演示运行中,在三个工作日内只需30个工作时间,安装,测试和激励345 kV变压器银行,每个100 MVA的三相单位,然后在常规网络操作中工作,包括过载条件。我们提供了一些关于所需站点测试的建议,因为与传统变压器相比,这些变压器更复杂。由于弹性变压器覆盖许多不同的变压器设计,并且可以在现场最短的时间内安装得更高的复杂性是合理的。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号