首页> 外文会议>CIGRE Session >HIGH CAPACITY TIDAL POWER PLANT UTILIZATION FOR ELECTRIC POWER PRODUCTION IN THE UNIFIED POWER SYSTEM OF RUSSIA
【24h】

HIGH CAPACITY TIDAL POWER PLANT UTILIZATION FOR ELECTRIC POWER PRODUCTION IN THE UNIFIED POWER SYSTEM OF RUSSIA

机译:俄罗斯统一电力系统中电力生产高容量潮汐发电厂利用

获取原文

摘要

According to the long term prospects it is assumed to build Mezen Tidal Power Plant in the North of the European part of Russia in the Mezen Gulf of the White Sea (to the North- East from Arkhanghelsk town). Mezen Tidal Power Plant, based on the up-to-date conceptions, has to be of extraordinary high installed capacity (8000-12000 MW). It requires a construction of unique hydroengineering installations in the sea, at a distance from the coast. The schedule of power distribution to the Tidal Power Plant consumers is exceptionally unfavourable for the consumers: the Tidal Power Plant operates in an impulse periodic mode. Every day the operating peaks shift in time approximately by 50 minutes. The largest period of capacity variationis is 28 days. Power generation of any month is identical and is constant from year to year. The Tidal Power Plant operation mode can be forecasted reliably for any prospective period. The capacity of Mezen Tidal Power Plant having a single-basin scheme of arrangement, is mainly duplicating, and if it is constructed, it won't allow to reduce considerably the startup of new generating capacities at the sites of other power plants. Large capacity and total electric power generation by Mezen Tidal Power Plant make it reasonable to consider a possibility and conditions of its utilization within the scope of a large power pool of the UPS of Russia European part. The analysis carried out has shown that Mezen Tidal Power Plant utilization is possible under conditions of hydroelectric pumped storage plant (PSP) construction for a Tidal Power Plant – PSP system and purposeful changing of the generation mix structure, otherwise the power system can not accept and efficiently utilize the power of Tidal Power Plant in a full scope. The optimum way of Tidal Power Plant efficient electric power utilization, from 24 Hours' and intra-24-hours' view point, is a creation of Tidal Power Plant + PSP Complex. For a transmission of electric power generated by Tidal Power Plant to the UPS network it may be worth while to construct +500 kV or +750 kV DC bipolar power transmission lines with appropriate substatations in a large power pool, in those locations where high loads are concentrated and there is a developed backbone network of high transmission capacity.
机译:根据假设建立梅津潮汐电站的俄罗斯在白海的梅津湾欧洲部分(从Arkhanghelsk镇的东北部)北方的长期前景。梅津潮汐电站的基础上,跟上时代的概念,必须是非常高的装机容量(8000-12000 MW)的。它需要一个建设中的海独特hydroengineering设施,在离海岸的距离。配电到潮汐发电站消费者的时间表是消费者非常不利的:潮汐发电站在冲动的周期性模式。每天操作峰时间约由50分钟转移。容量variationis的最大期限为28天。发电任何一个月的相同,并且是恒定的,从每年。潮汐发电站的操作模式能够可靠地对任何有意周期进行预测。有安排的单盆方案的梅津潮汐电站的能力,主要是重复的,如果它的构造,它不会允许显着地减少新的发电能力,启动其他电厂的地点。由梅津潮汐电站大容量和总发电量使其合理考虑的可能性和俄罗斯欧洲部分的UPS的功率大池的范围内,其使用的条件。进行的分析表明,梅津潮汐电厂的利用率,能够水力发电抽水蓄能植物(PSP)构造为一个潮汐发电站的条件下 - PSP 系统和发电组合结构的有目的的改变,否则电力系统不能接受和有效地利用潮汐电站的输出功率是在全范围内。潮汐电站效率的电力利用的最佳方式,从24小时内和24小时观点,是潮汐发电站+ PSP 复杂的创建。对于由潮汐发电站产生的UPS网络的电功率的传输可能是值得的构造500千伏或750条与在一个大的功率池适当substatations千伏直流双极输电线路,在那些高负荷位置浓缩并有高传输容量的发达骨干网络。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号