EXPEDITED FIELD ERECTED COOLING TOWER REPLACEMENT/UPGRADE WITH LIMITED SITE ACCESS AND AVAILABLE TOWER FOOTPRINT

机译:快速的现场竖立冷却塔替换/升级与有限的网站访问和可用塔脚印

获取原文

摘要

An innovative replacement and upgrade of a field erected cooling tower over an existing basin with limited site access. An aggressive construction schedule of eight weeks was followed with a limited total plant outage of three days. Cooling Tower performance was maximized including a decision mid-project schedule to increase the tower footprint by approximately 25% without increasing the size of the existing cold water basin. Tower was completely stick built and erected two weeks ahead of schedule with zero safety incidents.
机译:在现有的盆地上具有有限的站点访问的现有盆地的创新替代和升级。持续八周的积极施工时间表,总植物中断为期三天。冷却塔性能最大化,包括决定中项目时间表,以增加塔足迹约25%,而不增加现有冷水盆地的尺寸。塔完全坚持在附表提前两周内建造并竖立,零安全事件。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号