Estimation of pile lengths of a failed school block using the parallel seismic logging method

机译:使用并联地震测井方法估计失败的学校块的桩长

获取原文

摘要

The following conclusions can be made for the investigation ⅰ. Most of the driven pile lengths were found to be less than the recommended design length of 30m. Some of the short piles were also found to be on bedrock. ⅱ. At the settled locations, the lengths of the piles were found to be short and installed in the medium dense sand layer. ⅲ. PS tests can be a useful tool to determine approximately the lengths of driven piles in a failure investigation.
机译:以下结论可以进行调查Ⅰ。发现大多数从动桩长度小于推荐的设计长度为30米。一些短桩也被发现在基岩上。 Ⅱ。在稳定的位置,发现桩的长度短且安装在介质密集的砂层中。 Ⅲ。 PS测试可以是一个有用的工具,用于在故障调查中确定大约从动桩的长度。