D.C. United, the professional soccer team located in Washington, D.C., completed a 20,000 seat capacity stadium in July 2018 named Audi Field. The project initially considered a foundation system consisting of roughly 800 prestressed concrete driven piles configured in groups with pile caps. A value engineering alternative proposed in a design-build manner ultimately resulted in the use of 300 single element Auger Cast Piles (ACPs) for the foundation system. The ACPs ranged between 1.5 ft and 4 ft in diameter, were up to 85 ft in length, and were connected through a system of grade beams to accommodate large lateral induced loads. Limitations in conventional analytical methods were encountered during the structural design of the piles due to the complexity of the lateral loading and pile fixity conditions. An innovative approach using advanced finite element modeling that incorporated the framing effects of the grade beams was required to meet the strict movement criteria despite large lateral loads.
机译:2018年7月,位于华盛顿特区的职业足球队哥伦比亚特区联队(DC United)建成了一座可容纳2万人的体育场,名为奥迪球场(Audi Field)。该项目最初被认为是一个基础系统组成的大致800个预应力混凝土驱动桩配置成群的桩帽。以设计建造方式提出的价值工程替代方案最终导致300个单元螺旋钻孔桩(ACPS)用于基础系统。ACP直径在1.5英尺到4英尺之间,长度高达85英尺,通过一个坡度梁系统连接,以适应较大的横向诱导荷载。由于横向荷载和桩固定条件的复杂性,传统分析方法在桩的结构设计过程中遇到了限制。尽管存在较大的横向荷载,但仍需要采用先进的有限元建模方法,将坡度梁的框架效应纳入其中,以满足严格的移动标准。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号