Containment and dewatering of mine tailings with geotextile tubes at a Silver Mine in San Luis Potosi, Mexico

机译:墨西哥圣路易斯波罗斯银矿的土工织物管矿山尾矿的遏制和脱水

获取原文

摘要

During the night of January 2, 2015, a pipeline connecting the primary mine tailings impoundment to a secondary settling pond ruptured causing water and tailings material to be discharged outside of the tailings containment system. Fast action by the mine personnel prevented any contamination of the water supply of the local community. The mine had been operating for less than one year under a Mexican federal government permit. The mine management immediately notified the Mexican Federal Authorities who suspended the operating permit and established the necessary remediation steps and criteria for the mining company to resume mining operations. These steps included completing a full remediation of the spill area and providing the federal authorities a complete tailings management redesign. The new design must incorporate an alternative tailing storage facility. The technically acceptable and most economical alternative solution accepted by the federal authorities was geotextile tube containment and dewatering technology. This innovative technology adaptation design would receive all tailings generated from the mining operation. This paper will detail the required testing, design, installation, and operation of the geotextile tube system and analyze the economic impact that allowed the silver mine to restore full mining operations within 60 days of the rupture.
机译:在2015年1月2日的夜晚,将主要矿山尾矿蓄积的管道连接到二级沉降池塘破裂,导致水和尾矿材料在尾矿遏制系统外面排出。矿井人员的快速行动阻止了对当地社区供水的任何污染。该矿井在墨西哥联邦政府许可证下经营不到一年。矿山管理立即通知墨西哥联邦当局,暂停营业许可证,并设立了矿业公司必要的修复步骤和标准,以恢复采矿业务。这些步骤包括完成溢出区域的全面修复,并提供联邦当局完整的尾矿管理重新设计。新设计必须包含替代拖尾储存设施。联邦当局接受的技术上可接受和最经济的替代解决方案是土工织物管遏制和脱水技术。这种创新的技术适应设计将收到从采矿操作产生的所有尾矿。本文将详细介绍土工织物管系统的所需测试,设计,安装和操作,并分析允许银矿在破裂后60天内恢复全部采矿业务的经济影响。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号