High Performing Turf Reinforcement Mats Provide Stormwater Control in Large Drainage Channel

机译:高性能的草皮加固垫在大型排水通道中提供雨水控制

获取原文

摘要

In 2004, Illinois Department of Transportation District 2 Engineers were planning the extension of the Milan Beltway in the Quad Cities area of Northwestern Illinois, which include a long and highly visible drainage swale. Initial plans called for a rock riprap channel lining with cost estimates for this solution totaling about one million dollars. In addition to obvious concerns about the high price tag, the engineers were also concerned about aesthetics and maintenance of a rock lined channel. For all these reasons, the IL DOT engineers sought out a vegetated solution for this project. The channel adjacent to the beltway extension and the busy John Deere Expressway in Moline, Illinois needed to withstand the stormwater runoff created by the large roadways. During storm events the channel needed to withstand velocities of 20 ft/s and shear stress forces reaching 13 lbs/ft~2. 20,000 square yards of permanent Composite Turf Reinforcement Mats were installed in November of 2005. The late installation provided a real challenge to the project, requiring dormant seeding and leaving an unvegetated channel to withstand high flows through the winter months and into early spring. Moreover, 20 % of the upstream installation was not completed before winter. This area, just north of two 10 ft×10 ft box culverts, feeding the main channel, were left protected only by straw bale ditch checks. Several intense storms in late spring put the newly installed channel to the test. One storm produced 3.5 inches of rain within one day creating flashflood conditions, while a storm only a few weeks later produced 2 in/hr rainfalls resulting in standing water several feet deep. During these storm events, the upstream temporary straw bale ditch checks blew out totally, but the composite turf reinforcement mat provided the necessary erosion control to protect the channel. A site review in the spring of 2006 concluded that the lined channel had performed exceptionally well, and the site was fully vegetated within the first year. Compared to hard armor products the vegetated Turf Reinforcement Mats acted as a natural filter for stormwater runoff by allowing infiltration, entrapping sediments, and absorbing harmful pollutants, all while saving the Illinois DOT two-thirds of the original rock rip rap price tag.
机译:2004年,交通区2工程师伊利诺伊部门正计划在米兰的环城高速西北伊利诺伊州,其中包括一个漫长而非常明显的排水洼地的四城市区域的扩展。呼吁抛石渠道衬砌成本估计该解决方案共计约一百万美元的初步计划。除了对高价格标签明显的担忧,工程师们还关注美学和岩石林立通道的维护。对于所有这些原因,IL DOT工程师找到了这个项目有植被的解决方案。邻近于所述环形路延伸部和忙碌约翰迪尔高速公路莫林通道,伊利诺斯需要承受由大的道路创建的雨水径流。在暴雨期间承受达到13磅/英尺2〜20英尺/秒的速度和剪切应力的力所需要的信道。永久复合草皮增强垫的20000平方码被安装在2005年11月后期的安装提供了一个真正的挑战的项目,需要休眠的种子,留下的无植被通道通过冬季进入早春承受高流量。此外,上游安装的20%未冬之前完成。这个区域,只是北两10英尺×10英尺箱形暗渠,饲养的主要渠道,分别仅剩下由稻草沟检查保护。在春末几个强烈的风暴把新安装的通道测试。一个风暴产生的雨3.5英寸1天创造flashflood条件范围内,而风暴只有几个星期后产生了/小时2降雨造成的积水深数尺。在这些暴雨事件中,上游临时稻草沟检查完全吹灭,但复合草皮增强毡提供了必要的控制侵蚀,保护信道。在2006年春季现场审查的结论是,通道两旁有表现非常出色,而网站的第一年之内完全植被。相比于硬质装甲产品的植被草皮增强垫充当了雨水径流的自然过滤,允许渗透,包埋沉积物和吸收有害污染物,所有同时节省了原岩RIP说唱价格标签的伊利诺伊州DOT三分之二。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号