OBSERVATIONAL AND NUMERICAL EVALUATION OF DEFECTS IN DEEP MIXING METHOD COLUMNS USED FOR LNG PROCESS TRAIN STRUCTURAL FOUNDATION SUPPORT

机译:用于LNG工艺列车结构基础支持的深混合方法柱缺陷的观察和数值评估

获取原文

摘要

Between 2008 and 2009, more than 6,000, 23-m long deep mixing method (DMM) elements were constructed to support 124 concrete mats comprising the foundations for the process trains for an LNG facility. The Owner requested first-of-its-kind analyses and assessments to confirm the quality and reliability of the DMM foundation. This paper provides information on these assessments and the procedures used to ultimately conclude that a fit-for-purpose foundation system was constructed.
机译:在2008年至2009年期间,建造了超过6,000,23米长的深度混合方法(DMM)元件以支持124个混凝土垫,其包括用于LNG设施的过程列车的基础。业主要求首先进行分析和评估,以确认DMM基金会的质量和可靠性。本文提供了有关这些评估的信息,并且最终旨在结论适合型基础系统的程序。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号