PRIMARY ANALYSIS ON PERIODIC VARIATION OF EARTH PRESSURE ON HIGH RETAINING WALL OF ROCK-FILL DAM FOR YIXING PUMPED STORAGE POWER STATION

机译:宜兴泵浦储存电站高挡土坝高挡土墙周期变化的初步分析

获取原文

摘要

The dam of the Yixing pumped storage power station upper reservoir is CFRD, which is located on the steep slope inclining downstream, and a gravity retaining wall is sited at the dam heel to support the embankment of rockfill. The retaining wall is of "L" shape, with the cantilever of 25m in height. The wall has been under observation for 2 years since the completion, and the analysis of the observation date indicates: the main reason of the period variation of the earth pressure loaded on the retaining wall is the wall displacement caused by period temperature change on the downstream face and upstream face of the retaining wall, when the top of the wall moves upstream, the earth pressure increases; when the top of the wall moves downstream, the earth pressure decreases.
机译:Yixing泵送存储电站上层储存器的大坝是CFRD,其位于下游的陡坡上,并且在坝鞋跟上占据了重力挡土墙,以支撑岩石的堤防。挡土墙具有“L”形,高度25米的悬臂。完成后,墙已经观察到了2年以来完成,观察日期的分析表明:挡土墙上装载的地球压力的周期变化的主要原因是由下游的周期温度变化引起的壁位移挡土墙的面部和上游面,当壁的顶部上游移动时,地面压力增加;当壁的顶部下游移动时,地球压力降低。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号