首页> 外文会议>European Congress on Fliud Machinery for the Oil, Gas, and Petrochemical Industry >Major rerate of a process air compressor during a plant shutdown
【24h】

Major rerate of a process air compressor during a plant shutdown

机译:在工厂关闭期间重叠工艺空气压缩机

获取原文
获取外文期刊封面目录资料

摘要

The process air for a Polyester Intermediates plant was provided by the main air compressor (20MW) and a smaller subsidiary compressor (4.5MW). The small compressor was reaching the point where further operation would require significant expenditure without any performance improvements. This led to the plant seeking an alternate source of additional process air. Alongside this the process conditions had changed over time such that the main compressor was running significantly away from its original design point. Different options were assessed and a decision taken to uprate the main process air compressor. The operating constraints meant that the modification had to be designed such that construction and testing could be completed within the three week plant shutdown. This paper describes the design and engineering applied through the project process to minimise the risk involved with such major changes. To ensure all aspects were considered the project team included personnel from the operator, the technical consultant, the detailed design contractor, the vendor, and the construction contractor. The major challenges were around producing a suitable design capable of being installed and tested within the shutdown. The requirement was for an increase in mass flow rate of 20%, which combined with a reduction in discharge pressure equated to a 30% increase in discharge volume. This necessitated a new HP compressor casing which had to be mounted onto the existing bearing housings, internal modifications to the LP compressor and a larger first stage intercooler. The reuse of the existing bearing housings meant that it was not possible to carry out conventional API testing of the new components at the vendor's works before installation.
机译:聚酯中间体厂的工艺空气由主空气压缩机(20MW)和较小的辅助压缩机(4.5mW)提供。小型压缩机达到了进一步运行需要显着的支出而没有任何性能改进的程度。这导致了植物寻求替代工艺源的额外流程。除此之外,该过程条件随着时间的推移而变化,使得主要压缩机远离其原始设计点。评估了不同的选择,并对uprate主流压缩机进行了决定。操作约束意味着必须设计改进,使得建筑和测试可以在三周工厂关闭范围内完成。本文介绍了通过项目流程应用的设计和工程,以最大限度地减少此类重大变化所涉及的风险。为确保所有方面都被认为是项目团队包括来自运营商的人员,技术顾问,详细设计承包商,供应商和建筑承包商。主要挑战在生产能够在关机内安装和测试的合适设计。该要求的质量流速增加了20%,其与放电压力的降低相结合,排出量增加30%。这需要一种新的HP压缩机壳体,该壳体必须安装在现有的轴承壳上,对LP压缩机的内部修改和较大的第一级中冷却器。现有轴承外壳的再利用意味着在安装前不可能在供应商的作品中进行传统的API测试。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号