首页> 外文会议>Copper-Cobre international conference >Operational changes at Phelps Dodge's Morenci Mine
【24h】

Operational changes at Phelps Dodge's Morenci Mine

机译:菲尔普斯道奇莫伦西矿的操作变化

获取原文

摘要

In late 1999, Phelps Dodge announced that Morenci would curtail concentrator operations and crush high-grade leachable supergene ore exclusively for hydrometallurgical production in a project, which has become known as Mine-for-Leach (MFL). This would transform Morenci into a totally electrowon copper producer and expand hydrometallurgical production of copper by over 240 million pounds of copper per year to a total of 820 million pounds. The MFL project was commissioned during the first quarter of 2001 at a capital cost of approximately 220 million dollars. The transformation of the Morenci property into MFL was the result of the combination of many factors; recognizing the deposit would experience declining ore grades, the cyclic copper market, and technological developments in low cost hydrometallurgical processing. This paper reviews many of those changes including the most recent changes in the hydrometallurgical processes.
机译:1999年底,菲尔普斯道奇宣布,Morenci将在一个项目中遏制集中操作和粉碎高档可脱离的叠加矿石,该项目已被称为漏矿(MFL)。这会将Morenci转化为完全电向铜生产商,并将铜的液态冶金生产以超过2.4亿英镑的铜膨胀,共计8.2亿英镑。 MFL项目于2001年第一季度以约2.2亿美元的资本成本委托。 Morenci财产转变为MFL的结果是许多因素组合的结果;认识到押金将经历下降的矿石等级,循环铜市场和低成本湿法冶金加工的技术发展。本文审查了许多这些变化,包括湿法冶金过程最新变化。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号