OPTIMIZATION MODEL OF EXTERNAL RESOURCE ALLOCATION FOR RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEMS

机译:资源约束项目调度问题外部资源分配优化模型

获取原文

摘要

Construction project scheduling is crucial to project success. From the perspective of contractors, a practical schedule based on engineering experience not only improves the accuracy of project duration and cost estimation during the bidding process, but also facilitates the operation during project execution. This study employs Constraint Programming (CP) techniques to resolve resource-constrained project scheduling issues. A new scheduling model aiming for the minimization of total project cost, including resource usage and idle cost, is proposed in this paper. Most importantly, this paper introduces a new idea in resource-constrained project scheduling, namely the concept of external resources to enhance model feasibility for construction scheduling problems practice. A scheduling optimization engine coded in C++ is then developed to validate model feasibility and accuracy. The research results demonstrate the importance of external resources through case studies. Furthermore, the significance of critical resources is evaluated and discussed in this paper.
机译:建设项目调度对于项目成功至关重要。从承包商的角度来看,基于工程经验的实用时间表不仅可以提高项目持续时间和成本估计的准确性,而且还促进了项目执行期间的运作。本研究采用约束编程(CP)技术来解决资源受限的项目调度问题。本文提出了一种新的调度模型,旨在最大限度地减少总项目成本,包括资源使用和闲置成本。最重要的是,本文介绍了资源受限的项目调度中的新思路,即外部资源的概念,以提高建设调度问题实践的模型可行性。然后开发出在C ++中编码的调度优化引擎以验证模型可行性和准确性。研究结果证明了通过案例研究的外部资源的重要性。此外,在本文中评估和讨论了关键资源的重要性。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号