Restoration of concrete berth for Lae city port in Papua New Guinea

机译:巴布亚市新几内亚的Lae市港的混凝土泊位恢复

获取原文

摘要

The paper discusses some of the techniques that were used to ascertain the cause of damage and deterioration to berth No.4 of the Lae city wharf in Papua New Guinea. The paper also outlines a procedure that was used to repair and rehabilitate it. The berth comprising of a concrete deck, supported on steel tube piles was built in 1970, and by mid 1990's, it began showing signs of extensive visible deterioration with corrosion of steel piles and spalling of concrete. In the investigation, both visual survey and diagnostic testing was carried out to determine the process that was responsible for corrosion. The results indicated that high concentration of chloride ions in concrete was the primary cause of deterioration. Based on the investigation, remedial measures were proposed for the repair of the berth. The repair and restoration of the berth was successfully completed and tests done after the restoration work, estimated the life of the berth to have increased by 15 years.
机译:本文讨论了一些用于确定Papua新几内亚的Lae城市码头泊位损坏和恶化原因的技术。本文还概述了用于修复和恢复它的程序。该泊位包括一个混凝土甲板,支持钢管桩,于1970年建于1970年,并于1990年代中期,开始显示钢桩腐蚀和混凝土剥落的广泛可见恶化的迹象。在调查中,进行了视觉调查和诊断测试,以确定负责腐蚀的过程。结果表明,混凝土中的高浓度氯离子是劣化的主要原因。根据调查,提出了修复泊位的补救措施。泊位的修复和恢复成功完成并在恢复工作后进行测试,估计泊位的生命增加了15年。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号