Preliminary pile load test is usually carried out at the beginning of a piling contract. For the pile load test to be meaningful, it is usually instrumented. The pile instrumentation scheme will assist engineers in interpreting the soil-pile interaction behaviour of the pile, the unit skin friction of the various founding soil layers and the end bearing capacity. This will guides design engineer in the final design of a pile foundation system for a given project. However field instrumented pile, like any laboratory test, may be subject to inaccuracies. The understanding of the pile set-up and the way pile was constructed at the site is important. One of the factors is the equation used to analyze the instrumentation data. It involved parameters like cross-sectional area of pile and Young's modulus, which may be affected by construction method. This paper will present some local case studies of instrumented test piles. Through these case studies, factors that can affect test results will be presented. It wills highlights factors that may affect the instruments during installation and its results. This paper will also discuss why judgement of engineer is important when interpreting test result.
机译:初步桩载荷测试通常在打桩合同开始时进行。对于桩载试验有意义,通常是仪器。桩仪表方案将协助工程师解释桩的土桩相互作用行为,各种创始土层的单位皮肤摩擦和端部承载力。这将导致设计工程师在给定项目的桩基系统的最终设计中。然而,像任何实验室测试一样的现场仪表堆可能受到不准确的影响。在现场构建堆积和桩的理解是重要的。其中一个因素是用于分析仪器数据的等式。它涉及像桩和杨氏模量的横截面积,可能受到施工方法的影响。本文将提出仪器测试桩的一些本地案例研究。通过这些案例研究,将提出可能影响测试结果的因素。它将突出可能会在安装过程中影响仪器的因素及其结果。本文还将讨论为什么工程师判断在解释测试结果时很重要。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号