From the initial steam generator (SG) inspections at Darlington Nuclear Generating Station (DNGS), we know that the sludge accumulations on the secondary side tubesheets have been minimal. DNGS is a fairly new station but the experience at our older Ontario Hydro plants have shown that significant accumulations will happen. A pro-active strategy has been adopted for maintaining SGs that will minimize corrosion product accumulation and the potential for component degradation. During the four year planned Unit maintenance outages, SGs will be inspected and waterlanced using a waterlance system designed and built by Babcock & Wilcox International. This automated state-of the-art system also allows fully recorded inspections of the tubesheet/first half-lattice supports. Some of the key elements covered include results of the initial field application (May, 1995), system development and design, system qualification, cleaning performance, and lessons learned for future outages.
机译:从达灵顿核发电站(DNG)的初始蒸汽发生器(SG)检查,我们知道次级侧管板上的污泥累积一直很少。 DNG是一个相当新的车站,但我们旧的安大略省水电植物的经验表明,将发生重大的积累。采用了一种活跃的策略来维持SGS,以最大限度地减少腐蚀产品积累和组分降解潜力。在四年的计划单位维护中断期间,将使用由Babcock&Wilcox International设计和建造的防水系统进行检查和疏散SGS。这种自动化的最先进的系统还允许全部录制的管别/第一半格式支撑件检查。一些关键要素包括初始现场申请的结果(1995年5月),系统开发和设计,系统资格,清洁绩效以及未来中断的经验教训。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号