This paper reports on the construction management method to estimate the allowable vertical bearing capacity of the bored pile. The bearing capacity of the bored pile can be checked by carrying out the loading test. A method for confirming the bearing capacity of the bored pile without carrying out the loading test has not been established yet. However, the loading test is not common, as it requires significant cost and time.Therefore, management of pile construction was carried out while comparing and analyzing electrical current value, integrated electrical current value and drilling speed during pile excavation. In each layer, the layer thickness, and the support layer at the tip of the pile were confirmed with the above comparison and analysis.Next, the bearing capacity of the pile tip and the skin friction capacity of the pile were calculated using the individual layer thicknesses confirmed during pile excavation and the N value of the ground survey, then the allowable vertical bearing capacity of the pile was obtained by summing them.Finally, it was confirmed by loading test whether the calculated pile bearing capacity was attained. However, in order to quantitatively judge the vertical allowable bearing capacity without carrying out the loading test, it seems that still more data collection is necessary.
机译:本文报告了一种用于估计钻孔桩允许竖向承载力的施工管理方法。钻孔桩的承载能力可以通过进行载荷测试来检查。尚未建立用于在不进行载荷测试的情况下确定钻孔桩的承载力的方法。但是,负载测试并不常见,因为它需要大量的成本和时间。 因此,在对桩基开挖过程中的电流值,积分电流值和钻孔速度进行比较和分析的同时,要进行桩的施工管理。通过以上比较和分析,确认了各层的层厚和桩顶的支撑层。 接着,利用在开挖时确认的各层厚度和地面测量的N值,计算出桩尖的承载力和桩的表皮摩擦力,求和后求出桩的容许竖向承载力。他们。 最后,通过载荷试验确认是否达到计算出的桩承载能力。但是,为了在不进行负载测试的情况下定量地确定垂直允许的承载能力,似乎还需要更多的数据收集。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号