Employing Combined Technologies To Save Combined Brick Sewers: Trenchless Rehabilitation In Omaha, Nebraska

机译:使用组合技术来节省组合砖下水道:内布拉斯加州奥马哈的无沟渠修复

获取原文

摘要

The Omaha combined storm/sanitary sewer (CSS) rehabilitation at the intersection of 7th & Jones is notable for several reasons. The pipelines involved were very large and old; two sewers running in parallel, made of hand laid brick with diameters of 7.5 feet and 8.5 feet. Initial collapse was sudden and spectacular, stopping traffic and closing a major Omaha intersection, in an important industrial area, for several weeks. Further inspection revealed major degradation in an additional 55 feet of the sewer lines. Near the area of collapse, the parallel sewer lines connected with additional large structures, including a 20' x 20' box culvert, gate valves, large (6-feet) incoming lines, and large retaining structures. This paper discusses the preparation and rehabilitation of the two parallel brick CSS structures.
机译:第七和琼斯交叉路口的奥马哈雨水/污水处理厂(CSS)联合修复项目值得注意,原因有几个。所涉及的管道很大而且很旧;两个下水道平行运行,由直径为7.5英尺和8.5英尺的手工砌砖制成。最初的倒塌是突然的,而且十分壮观,阻止了交通,并关闭了重要工业区中主要的奥马哈交叉口,持续了数周。进一步检查发现,下水道的另外55英尺出现了严重退化。在坍塌区域附近,平行的下水道管线与其他大型结构相连,包括20'x 20'箱形涵洞,闸阀,大型(6英尺)进水管线和大型固定结构。本文讨论了两个平行砖CSS结构的准备和修复。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号