Breathing 20 Years of Life into Expired PCCP Segments—How a Regional Medical Center Was Able to Save Their Pipeline

机译:在过期的PCCP细分市场中呼吸20年的生命—区域医疗中心如何能够挽救其管道

获取原文

摘要

Just imagine it is the dead of winter in Milwaukee, Wisconsin, and you are asked to repair eleven segments of dual 36-inch prestressed concrete cylinder pipe (PCCP) and have it completed and back in service in less than four weeks. A regional medical center in the area doesn't have the budget to repair the whole line but needs the dual pipe system to last for another 20 years when the funds come available. The eleven segments were identified through nondestructive evaluation and deemed in need of rehabilitation to last the required 20 years. There are a multitude of trenchless rehabilitation solutions available (i.e. CIPP, spray in place, slip lining, etc.), but which one provides segmental repair option and can be completed within the owner's compressed schedule? In the end, the use of carbon fiber reinforced polymers (CFRP) was selected as the ideal choice. This paper will examine the owner's decision to use CFRP, the design process, and the successful installation of the CFRP system in the difficult conditions.
机译:试想一下,这是威斯康星州密尔沃基的冬日之死,您需要修理11段双36英寸预应力混凝土圆柱管(PCCP),并在不到四周的时间内完成并重新投入使用。该地区的区域医疗中心没有预算来修复整条生产线,但在资金到位后,需要双管系统才能再使用20年。通过无损评估确定了这11个部分,并认为需要恢复才能持续20年。有许多可用的非开挖式修复解决方案(即CIPP,现场喷涂,衬砌等),但是哪一个提供分段修复选项,并且可以在所有者压缩的时间表内完成?最后,选择碳纤维增强聚合物(CFRP)作为理想选择。本文将探讨所有者在困难条件下使用CFRP的决定,设计过程以及CFRP系统的成功安装。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号