CLAIREVILLE ‘MISSILE’ SOLVES NPS 42 HDD INSTALLATION DIFFICULTY IN TORONTO

机译:CLAIREVILLE'MISSILE'解决了多伦多NPS 42 HDD安装困难

获取原文

摘要

At 1,185 metres (3888 ft.), one of the longest HDDs on the Enbridge Greater Toronto Area (GTA) project in 2015 was the NPS 42-inch crossing under the Claireville Reservoir and Finch Avenue. Originally planned as two bores, the proximity of the exit points made it clear that a single HDD would be more appropriate. Because of the length of the crossing and the environmental requirements of crossing the reservoir, it was also one of the more critical crossings to be directionally drilled on the project. The majority of the bore length was in shale bedrock with no surface casing utilized. As a result the Finch Ave HDD and the Clairveille Reservoir HDD were combined in the design stage to make a single, long HDD where an intersect was considered. Due to the critical nature of this crossing, it was the first HDD on the project to be constructed. Construction started in early January of 2015. Difficulty was encountered during pullback of the NPS 42 product pipe and Mears, the HDD contractor, designed an innovative telescoped pullhead to assist with the pipe installation. This paper will discuss the crossing design, the difficulties encountered, and the innovative solution dubbed the ‘Clareville missile’ which solved the installation problem. With a total of 14 significant HDDs and 3 Direct Pipe installations the GTA project was a significant project for Enbridge Gas from a trenchless respect.
机译:在2015年,eNBridge大多雅地区(GTA)项目中最长的HDDS是185米(3888英尺),是Claireville水库和Finch Avenue下的NPS 42英寸横穿。最初计划作为两个孔,出口点的接近使得单个硬盘更合适。由于交叉的长度和过水库的环境要求,它也是在项目上方向钻探的更为关键的交叉路口之一。大部分孔长度在页岩基岩中,没有使用表面套管。结果,Finch Ave HDD和Clairveille储层HDD在设计阶段组合以制造一个单一的长HDD,其中被考虑交叉。由于这种过境的危急性质,它是第一个待建造的项目的硬盘。建筑于2015年1月初开始。在NPS 42产品管道和MEARS的回调期间遇到困难,HDD承包商设计了一种创新的伸缩拉头,可以帮助管道安装。本文将讨论交叉设计,遇到的困难,并将创新的解决方案称为“克拉维尔导弹”,解决了安装问题。总共14个显着的HDD和3个直接管道安装,GTA项目是一项从一个绝妙的尊重中的盲人气体的重要项目。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号