WESTMINSTER DRIVE UNDERPASS - ACCELERATED BRIDGE CONSTRUCTION USING GIGO (GET IN-GET OUT) BRIDGE CONCEPT

机译:威斯敏斯特驱动器地下通道-使用GIGO(进出)桥梁概念的加速桥梁建设

获取原文

摘要

The Ministry of Transportation Ontario (MTO), in partnership with consultants and contractors, developed a method for accelerated bridge construction called Get in-Get out Bridge or GiGo Bridge. The GiGo Bridge concept is an Accelerated Bridge Construction (ABC) technique for replacing bridges over freeways, in 45 days or less, with a full closure of the crossing road. The concept requires that bridge components be prefabricated in advance of the on-site work. This has the advantage of shifting a substantial portion of the work into the winter months, freeing up staff resources and equipment for the summer months. Additional benefits of GiGo Bridge include shorter disruptions to traffic as well as enhanced safety, since workers have less contact with traffic during the project. In 2014, the Westminster Drive Underpass on Highway 401 in London, Ontario, was successfully replaced using the GiGo Bridge concept. The new, two-span integral abutment bridge consists of a number of prefabricated elements, including precast concrete abutments, wingwalls, and pier cap; and steel box girders. However, the accelerated bridge construction feature that is of primary interest in this project, and that is key to the GiGo Bridge concept, is the use of 6 prefabricated, 95-tonne supermodules, each of which consists of a steel box girder with a cast-in-place concrete deck. Based on the success and lessons learned from the Westminster Drive project, MTO will be using the GiGo Bridge concept on other projects, including the replacement of the Highway 401/Highway 19 Underpass in Ingersoll in 2017.
机译:安大略省交通部(MTO)与顾问和承包商合作,开发了一种称为Get in-Get out Bridge或GiGo Bridge的桥梁加速施工方法。 GiGo桥梁概念是一种加速桥梁建设(ABC)技术,用于在45天或更短的时间内完全关闭交叉路口来更换高速公路上的桥梁。该概念要求在现场工作之前预制桥梁组件。这样做的好处是将大部分工作转移到了冬季,从而释放了夏季的员工资源和设备。 GiGo Bridge的其他好处包括缩短了交通中断时间,并增强了安全性,因为在项目期间工人与交通的接触减少了。 2014年,安大略省伦敦市的401号高速公路上的威斯敏斯特大道地下通道已成功使用GiGo桥概念进行了更换。新的两跨整体式桥台由许多预制构件组成,包括预制混凝土桥台,翼墙和墩台。和钢箱梁。但是,此项目中最重要的加速桥梁建设功能(也是GiGo桥梁概念的关键)是使用6个预制的,重达95吨的超级模块,每个模块由一个带铸件的钢箱梁组成就地混凝土甲板。基于从威斯敏斯特大道项目获得的成功和经验教训,MTO将在其他项目中使用GiGo桥概念,包括在2017年更换英格索尔的401 / Highway 19地下通道。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号