This work describes the ASTEC simulation of a station black-out (SBO) scenario in a German 1300 MW_(el) KONVOI NPP with subsequent re-flood of a partly degraded core performed in the frame of the European research project CESAM in the 7th framework program. During the assumed SBO sequence no electrical supply is available on the main voltage levels including the failure of all electrical emergency systems. The simulation results of ASTEC show the capability of the system code to depict the occurring phenomena and the accident scenario reasonably. Uncertainties can be seen in the simulation of degradation phenomena, especially depicting the re-flooding phase, whereas the general behavior of the calculated NPP is kept. Furthermore, the severe accident management (SAM) measure, the restore of electricity and high pressure injection (HPI), is capable to transfer the system into stable conditions after the desired accident.
机译:这项工作描述了德国1300 MW_(el)KONVOI NPP电站停电(SBO)情景的ASTEC模拟,随后在欧洲研究项目CESAM的第七框架中对部分退化的岩心进行了重新注水。程序。在假定的SBO序列期间,主电压电平上没有可用的电源,包括所有紧急电气系统的故障。 ASTEC的仿真结果表明,系统代码能够合理地描述发生的现象和事故情况。在退化现象的模拟中可以看到不确定性,尤其是在描述再注水阶段时,而所计算的NPP的一般行为却得以保留。此外,严重事故管理(SAM)措施,电力恢复和高压喷射(HPI)能够在发生所需事故后将系统转换为稳定状态。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号