MACDONALD BRIDGE SUSPENDED SPANS DECK REPLACEMENT: ENGINEERING CHALLENGES AND SOLUTIONS

机译:麦克唐纳德大桥悬吊式甲板更换:工程方面的挑战和解决方案

获取原文

摘要

The Angus L. Macdonald Bridge is a major suspension bridge that crosses Halifax Harbour in Halifax, Nova Scotia, Canada. The deck of the suspended spans has reached the end of its functional life and design of a deck replacement scheme is under way. Deck segment fabrication will begin in 2014 and construction will span 2015 - 2016. On this project, a variety of significant engineering challenges have been encountered because of the complexity of replacing the deck at night with the bridge open to traffic during the day and because the design engineers are preparing the deck erection sequences scheme. This approach will streamline the construction process and lower overall project risk. Main cable dehumidification is being considered for the project.
机译:安格斯·麦克唐纳大桥是横跨加拿大新斯科舍省哈利法克斯的哈利法克斯港口的主要悬索桥。悬跨的甲板已经达到其使用寿命,并且甲板更换方案的设计正在进行中。甲板段的制造将于2014年开始,建造时间跨度为2015年至2016年。在此项目上,由于夜间更换桥面和白天通车的桥的复杂性,并且遇到了许多重大工程挑战。设计工程师正在准备甲板安装顺序方案。这种方法将简化施工过程并降低总体项目风险。该项目正在考虑对主电缆进行除湿。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号