Temporary Excavation Support System – A Case Study in Virginia

机译:临时挖掘支持系统 - 以弗吉尼亚州为例

获取原文

摘要

A temporary excavation support system was installed for construction of a footing along a 45° site slope for a five-story parking garage at George Mason University in Fairfax, Virginia. This paper evaluates the performance of the temporary excavation support system for this project. The site is located within Piedmont Physiographic Province and is underlain by undocumented fill, residual soil, and disintegrated rock. The residual soils predominantly consist of fine sandy silts and silty fine sands with mica. The computer programs “ct-Shoring” and PLAXIS were used for the analyses and design of the temporary excavation support system. An 8.5-ft tall cantilever soldier pile wall was used to support the 15-ft high 45° site slope at the back of the wall. The maximum deflection for the cantilever wall was estimated to be less than 1.5 inches based on the analyses and design and construction considerations. The observed final wall deflection was less than 1.5 inches.
机译:安装了临时挖掘支持系统,用于沿着弗吉尼亚州费尔法克斯乔治梅森大学的五层楼停车库沿着45°场地坡度建造一座脚踏。本文评估了该项目临时挖掘支持系统的性能。该网站位于皮埃蒙特地理学省内,由未记录的填充,残余土壤和解体岩石下划线。残留的土壤主要由细砂淤泥和丝状细砂组成。计算机程序“CT-Shoring”和PLAXIS用于分析和设计临时挖掘支持系统。 8.5英尺高的悬臂式士兵桩壁用于支撑墙壁后部的15英尺高45°场地斜坡。悬臂墙的最大偏转估计基于分析和设计和施工考虑,估计小于1.5英寸。观察到的最终壁偏转小于1.5英寸。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号