首页> 外文会议>Geotechnical Engineering in the Information Technology Age >Temporary Excavation Support System – A Case Study in Virginia
【24h】

Temporary Excavation Support System – A Case Study in Virginia

机译:临时开挖支持系统–以弗吉尼亚州为例

获取原文
获取原文并翻译 | 示例

摘要

A temporary excavation support system was installed for construction of a footing along a 45° site slope for a five-story parking garage at George Mason University in Fairfax, Virginia. This paper evaluates the performance of the temporary excavation support system for this project. The site is located within Piedmont Physiographic Province and is underlain by undocumented fill, residual soil, and disintegrated rock. The residual soils predominantly consist of fine sandy silts and silty fine sands with mica. The computer programs “ct-Shoring” and PLAXIS were used for the analyses and design of the temporary excavation support system. An 8.5-ft tall cantilever soldier pile wall was used to support the 15-ft high 45° site slope at the back of the wall. The maximum deflection for the cantilever wall was estimated to be less than 1.5 inches based on the analyses and design and construction considerations. The observed final wall deflection was less than 1.5 inches.
机译:在弗吉尼亚州费尔法克斯的乔治·梅森大学,安装了一个临时挖掘支持系统,用于沿45°场地坡度建立基础,用于五层楼的车库。本文评估了此项目的临时挖掘支持系统的性能。该地点位于皮埃蒙特自然地理省内,并且被未记载的填充物,残留土壤和崩解的岩石所掩盖。残留的土壤主要由细砂质粉砂和粉云母细粉砂组成。计算机程序“ ct-Shoring”和PLAXIS用于临时挖掘支持系统的分析和设计。使用8.5英尺高的悬臂士兵墙支撑墙后部15英尺高的45°场地坡度。根据分析,设计和施工考虑,悬臂墙的最大挠度估计小于1.5英寸。观察到的最终壁挠度小于1.5英寸。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号