Discussion of Blast Vibration of Construct Little Space Tunnel

机译:建筑小空间隧道爆破振动的探讨

获取原文

摘要

According to construction of a little space tunnel in Jiaojin Mountain of Dalian city, based on the theory of rock damaged caused by blasting and monitoring data of damnified rock in-situ experiments, a series of tunnel blasting experiments are carried out, the standard of blasting vibration velocity is increased from the present 4~6cm/s to 10~15cm/s. According to this standard, advance of blasting is 8~9m. Construction schedule and construction cost are reduced. In the end the new tunnel was constructed safely, fast and economically. Considering numerical simulation and strength of rock and concrete, Safety of the existing tunnels is analyzed and the blasting vibration velocity standard of a litter space is discussed.
机译:根据大连市角金山一条小空间隧道的建设,根据爆破对岩石的破坏理论,以及在现场进行的有毒岩石现场监测数据的监测,进行了一系列隧道爆破试验,确定了爆破标准振动速度从现在的4〜6cm / s增加到10〜15cm / s。根据该标准,爆破进度为8〜9m。减少了施工进度,降低了施工成本。最后,安全,快速,经济地建造了新隧道。考虑到数值模拟和岩石和混凝土的强度,分析了现有隧道的安全性,并讨论了凋落空间的爆破振动速度标准。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号