The Yixing Pumped Storage Project objective is to increase the overall efficiency of the power sector in Jiangsu Province. It eases acute peaking problems and improves the generation mix that will create the conditions for more flexible dispatch and improved supply reliability, an essential requirement for well wellfunctioning competitive markets. The project components are: 1) -functioning construction of the Yinxing pumped storage power plant, a new upper reservoir, new main dam and subsidiary dam, and the underground powerhouse? 2) assistance to the restructuring of the power sector? and 3) construction of a double circuit transmission line to connect the Yixing pumped storage plant to the East China 500 KV network. The project will contribute to energy sector transition from a fully state stateowned monopolistic sector to a diversely owned, market owned oriented sector in which are promoted clean fuels, renewable energy, energy efficiency and assistance to poor western areas to develop their energy resources for local growth and export to other regions. The basic cycle of operation consist of generating during peak load periods and pumping during off – peak periods. The pl plant can also run in condenser mode to stabilize the grid ant voltage. The Yixing pumped storage power plant consist of four sets of vertical shaft, single singlestage, -stage, Francis, reversible Units, each with a capacity of 250MW. (total plant capacity of 1000MW). ABB as a subcontractor to GE on the project is providing CSCS (computer supervisory control system) and auxiliary electrical systems. ABB will deliver control, protection and excitation systems, static frequency converters, generator circuit breakers, station se service systems and rvice cabling. The project is implemented jointly by ABB Canada and ABB Norway with active support from ABB China. The Paper he will introduce the solution of CSCS from ABB for Yixing Pumped Storage Power Station.
机译:宜兴抽水蓄能项目的目标是提高江苏省电力部门的整体效率。它缓解了尖峰问题,并改善了发电组合,从而为更灵活的调度和改善的供电可靠性创造了条件,这是运作良好的竞争市场的基本要求。该项目的组成部分是:1)-银兴抽水蓄能电站,新的上水库,新的主水坝和副水坝以及地下厂房的功能性建设? 2)协助电力部门重组? 3)修建一条将宜兴抽水蓄能电站连接到华东500 KV电网的双回输电线路。该项目将有助于能源部门从完全国有的垄断部门过渡到多元化,以市场为导向的部门,在其中促进清洁燃料,可再生能源,能源效率的发展,并向西部贫困地区提供援助,以发展其能源资源以促进当地增长并出口到其他地区。基本的运行周期包括在高峰负荷期间发电和在非高峰期进行抽水。 PL工厂还可以在电容器模式下运行,以稳定电网蚂蚁电压。宜兴抽水蓄能电站由四套立轴,单级,单级,弗朗西斯可逆机组组成,每台容量为250MW。 (总工厂容量为1000MW)。作为该项目GE的分包商,ABB正在提供CSCS(计算机监控系统)和辅助电气系统。 ABB将提供控制,保护和励磁系统,静态变频器,发电机断路器,电站服务系统和服务电缆。该项目由加拿大ABB和挪威ABB共同实施,并得到了ABB中国的积极支持。他将介绍ABB的CSCS宜兴抽水蓄能电站的解决方案。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号