THE KEY TECHNIQUE OF LONG SHOU 2ND STAGE HYDROPOWER STATION CONSTRUCTION

机译:龙寿二期水电站施工关键技术。

获取原文

摘要

Ngshou 2nd Stage Hydropower Station in Gan Su Provice lies in the very cold and often earthquake and dry region, the mountain is steep, the dam type is seldom seen grotesquely type concrete face rockfill dam,the biggest dam height 146.5 m, construction term is rather bad, and the work period is short, and the mission is heavy. For insure the construction speed and the quantity, through the cautiously analysising with the argument,we change the high digitated wall's normal concrete to RCC and adopt the technique of cave blowing up in the moraine material . This makes construction speed greatly. Counteract that extruded wall fored normal regulations of the front-panel dam upper stream ramped to start construction method.Construction practice shows that the mat layer material with extruded wall do not take place breaking away phenomenon and combine to stipulation concrete front-panel very small, that have no need to draw brushing the pitch the etc. to insulate.At the same time in the digitated plank, discharge tower of release excessive tunnel reinforcing bar under construction adopt the technique of the strong straight screw thread in reinforcing bar etc. conjunction, so we get the good result of construction term and profit.
机译:甘肃省伍寿二级水电站位于非常寒冷,经常发生地震和干旱的地区,山势陡峭,坝型很少见怪异型混凝土面板堆石坝,最大坝高146.5 m,工期相当不好,工作时间短,任务重。为了确保施工速度和数量,通过对参数的谨慎分析,我们将高指墙的普通混凝土改为碾压混凝土,并采用了在冰ora材料中吹孔的技术。这极大地提高了施工速度。挤塑墙违反了前面板坝上游正常规范的斜面开始施工方法。施工实践表明,挤塑墙面垫层材料不会发生脱落现象,并结合在一起规定混凝土前面板很小,同时在数字化木板上,正在施工的释放过量隧道钢筋的排料塔采用了钢筋等强力直螺纹技术的结合,因此,我们获得了建设期和利润的良好结果。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号