Geotechnical Investigations and Proposal for Stabilization and Recovery Slope on Highway BR-010 Stretch in Aparecida do Rio Negro to Goiatins, Tocantins, Brazil

机译:巴西里约热内卢阿瓦雷西达-里奥内格罗至戈亚廷斯的BR-010高速公路延展路段的岩土工程勘察和稳定和恢复坡度的建议

获取原文

摘要

This article presents the results of geotechnical studies and proposals to stabilize embankments referring to cuts 16, 23, 25, 30 and 31 of the BR-010 referring to Aparecida do Rio Negro a Goiatins, State of Tocantins. The study consisted in the execution of a field incursions program for verification of geotechnical conditions along the indicated stretch, running lab tests, and stability analysis of embankments in order to indicate solutions to cuts made necessary for the completion of the highway. In terms of characterization of the problem, it presents part of the photographic survey conducted in November 2007 with the conditions of the most critical slopes. There is in the pictures that the side slopes to the highway were in the process of degradation and (or) progressive destabilization requiring urgent interventions aimed at mitigating the ongoing problems. In terms of geometry, the slope had heights up to approximately 35 m. To determine the parameters necessary to verify the stability of embankments using three undeformed blocks corresponding soil to cuts 25 and 31. Samples of identifications are presented and the summary of the results of geotechnical tests performed and certain parameters. In laboratory tests, it was found that the strength parameters (cohesion and angle of friction) diverged somewhat from the usual laboratory parameters obtained in soils. This behavior was due to the fact that the heterogeneity of the samples for the presence mainly of discontinuities in the collected blocks. Before the run stability analysis and field surveys, it was found, the need for actions aimed at solving problems for marginal slope to the highway. Thus, due to the proximity of the intense rainy season, it was proposed the reconstruction of slope with surface protection of them aimed at stabilization and protection against erosion, as well as the execution of superficial and deep drainage. Aiming to further verify the possible degradation of the slopes by rain, was sought in INMET's website (National Institute of Meteorology) precipitation to the region. It was found that for the time in January, February and March rainfall is considerably high, which could further compromise the integrity of the executed cuts. Faced with this possibility, he indicated consider the emergency actions that could prevent this degradation. Actions such as the reduction and protection of embankments shown in the study.
机译:本文介绍了土力工程研究的结果,并提出了稳定路堤的建议,这是指BR-010的第16、23、25、30和31条切口,这是托康丁州的Aparecida do Rio Negro a Goiatins。这项研究包括执行一项现场入侵计划,以验证沿所示延伸段的岩土条件,进行实验室测试以及对路堤进行稳定性分析,以指出解决方案,以解决高速公路完工所必需的问题。就问题的特征而言,它介绍了2007年11月进行的摄影调查的一部分,其中包括最严重的斜坡条件。图片中显示高速公路的边坡正在退化和(或)逐渐失去稳定,需要采取紧急干预措施以减轻持续存在的问题。在几何形状方面,该斜坡的高度可达约35 m。为了确定必要的参数来验证路堤的稳定性,使用了三个未变形的块体,分别对应于切口25和31的土壤。给出了识别样本,并汇总了岩土工程测试的结果和某些参数。在实验室测试中,发现强度参数(内聚力和摩擦角)与在土壤中获得的常规实验室参数有所不同。此行为是由于以下事实:样品的异质性主要是收集到的区块中存在不连续性。在进行行驶稳定性分析和现场调查之前,已经发现需要采取措施来解决高速公路边坡的问题。因此,由于雨季临近,建议对斜坡进行表面保护,以稳定和防止侵蚀,并进行浅层和深层排水。为了进一步验证降雨可能造成的斜坡退化,在INMET网站(国家气象研究所)上对该地区的降水进行了调查。结果发现,在一月,二月和三月的降雨量相当高,这可能会进一步损害已执行切割的完整性。面对这种可能性,他指出要考虑可以防止这种情况恶化的紧急行动。研究中显示了诸如减少和保护路堤之类的行动。

著录项

相似文献

  • 外文文献
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号