Optimizing a Breakwater Design with Multiple Constraints

机译:具有多个约束条件的防波堤设计优化

获取原文

摘要

This paper describes the innovative breakwater design and construction methodology for a new 400-foot-long breakwater at the Naval Air Station (NAS) Whidbey Island Fuel Pier located on Whidbey Island in Washington State. The breakwater was designed to enable construction within the challenging and highly restrictive existing conditions, environmental requirements, and construction scheduling constraints. The use of precast concrete construction was maximized to enable demolition of existing features and new construction within the permitted 7-month "fish window" from July 15, 2015 to February 14, 2016. Other environmental constraints included the exclusive use of concrete piles, a limited number of piles overall, use of an impact hammer and jetting only for pile installation, avoidance of eel grass areas, and no use of a vibratory hammer for pile extraction or installation. Further, a functional breakwater was required to be in place by the beginning of the storm season on October 15, 2015 in the form of either a permanent installation or temporary shelter. The breakwater comprises precast prestressed concrete vertical and batter piles, precast concrete wave panels, and cast-in-place concrete pile caps. Restrictions on the number of piles required carefully optimizing the design of vertical and batter piles to balance the requirements of wave loads and seismic loads for long slender piles and cohesive soils. This project showcases design innovation and optimization resulting from the partnership between the design-build contractor and designer for an environmentally sensitive site that is home to at least four endangered species: salmon, southern resident killer whales, marbled murrelets (birds), and bull trout.
机译:本文介绍了位于华盛顿州惠德比岛的海军航空站(NAS)惠德比岛加油站的新型400英尺长防波堤的创新防波堤设计和施工方法。防波堤的设计旨在在充满挑战和高度限制性的现有条件,环境要求和施工进度约束条件下进行施工。从2015年7月15日至2016年2月14日,在允许的为期7个月的“鱼窗”内,最大限度地利用了预制混凝土结构,以实现对现有功能和新结构的拆除。其他环境限制还包括混凝土桩的专有使用,总体而言,桩的数量有限,仅使用冲击锤和喷射进行桩安装,避免出现鳗鱼草皮,并且不使用振动锤进行桩的提取或安装。此外,要求在2015年10月15日暴风雨季节开始之前以永久性安装或临时避难所的形式部署功能性防波堤。防波堤包括预制预应力混凝土竖桩和面糊桩,预制混凝土波浪板和现浇混凝土桩帽。对桩数量的限制要求仔细优化垂直桩和面糊桩的设计,以平衡细长桩和粘性土的波浪荷载和地震荷载的要求。该项目展示了设计建造承包商与设计师之间的合作关系所带来的设计创新和优化,该地点对环境敏感,这里至少有四个濒危物种:鲑鱼,南方常驻虎鲸,大理石marble鱼(鸟)和鳟鱼。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号