Analysis of Construction Productivity Using Schedules Loaded with Labor and Material Resources

机译:使用带有人工和材料资源的进度表分析建筑生产率

获取原文

摘要

Comparison of actual productivity to target productivity alone does not offer enough input for the root-cause analysis of productivity variation. As an example, actual productivity will be equal to target when there is a reduction in both labor assignment and in the number of units produced. While this shows a good productivity number compared to baseline productivity, there will be an undesirable impact on the project schedule. This paper presents a tool that helps analyze the reasoning of productivity deviation from a target. Schedules loaded with both material and labor resources allow for time-phased productivity analysis. The paper presents nine scenarios for output (material resources) versus input (labor resources). Each scenario will help in the root-cause analysis of productivity variations. Lower productivity with planned labor resources indicates lower skills of resources, while lower productivity with higher labor hours indicates less planning, management effectiveness, or the unavailability of material. In addition to these types of analyses, the paper gives definitions and a literature review of the construction productivity.
机译:仅将实际生产率与目标生产率进行比较并不能为生产率变化的根本原因分析提供足够的输入。例如,当劳力分配和单位数量减少时,实际生产率将等于目标。尽管这显示出与基准生产率相比好的生产率数字,但将对项目进度产生不良影响。本文提出了一种工具,可以帮助分析生产率偏离目标的原因。附有物料和人工资源的计划表允许按时间分段进行生产率分析。本文介绍了产出(物质资源)与投入(劳动力资源)相对的九种情况。每种情况都将有助于分析生产率差异的根本原因。具有计划的劳动力资源的较低生产率表示资源技能较低,而具有较高的劳动时间的较低生产率表示较低的计划,管理有效性或材料不可用。除了这些类型的分析外,本文还给出了建筑生产率的定义和文献综述。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号