Cerro da Mina reservoir for industrial water: aspects of the design and construction

机译:塞罗达米纳工业水库:设计与施工

获取原文

摘要

The Cerro da Mina reservoir was built to store the industrial water used in the ore production. The reservoir comprises, on the west and north sides, a rockfill embankment and, on the east and south sides, excavated rock slopes. The rockfill embankment maximum height is 30 m and has a volume of about 452 000 m~3. The excavated rock slopes have a maximum height of 21 m. All the reservoir area is waterproofed by a double lining system. The storage capacity is 1 450 000 m~3. The reservoir is equipped with a syphon auxiliary discharge, a spillway and an intersection channel to divert the pluvial water. This paper presents the main aspects of the reservoir final design, focusing on the rockfill embankment zoning and on the geomechanical characterization of the construction materials. The quality control of the embankment and the analysis of the settlements measured during construction are also presented.
机译:塞罗达米纳(Cerro da Mina)水库的建立是为了存储矿石生产中使用的工业用水。该水库在西侧和北侧包括一个堆石路堤,在东侧和南侧包括一个开挖的岩石斜坡。堆石路堤的最大高度为30 m,容积约为452 000 m〜3。开挖的岩石斜坡的最大高度为21 m。所有储水区均采用双衬砌系统进行防水处理。存储容量为1 450 000 m〜3。该水库配有虹吸辅助排水口,溢洪道和相交通道,以转移小水。本文介绍了储层最终设计的主要方面,重点是堆石路堤分区和建筑材料的地质力学特征。还介绍了路堤的质量控制以及在施工过程中测量到的沉降的分析。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号