【24h】

Smart Grid through Integrated SCADA System-Karnataka Model-A Case Study

机译:通过集成SCADA系统实现智能电网-卡纳塔克模型-案例研究

获取原文

摘要

It is analyzed that most of the SCADA Networks in India are not complete in its totality. Hence, Smart Grid kind of approach has remained in papers. If some Utilities have EMS SCADA Systems at 400 and 220 kV levels, others have DMS SCADA at 33 and 11 kV levels. There is no State in India except Karnataka, which has a complete SCADA Network from 11 kV level to 400 kV level. I was the Architect of this Network in Karnataka, popularly known as “Karnataka Model” throughout the World.The National Electricity Policy 2003 (India) envisaged some vital requirements in the Utility Networks, consequent to reforms like unbundling of Utilities into Generation, Transmission and Distribution domains like: 1. Adapting Open Access System, 2. Providing Line Flows in real time to Open Access Customer (OAC) and Utility, 3. Making the activities of the Electricity Utility Transparent 4. Extending ABT Type of Operations down to ESCOMs5. Creating Separate Load Despatch Centres to ESCOMs to manage their own Grid, 6. Creating Separate Load Despatch Centres for Transmission Operators 7. Making Energy Loss calculations at all Voltage levels more automatic,This made Karnataka to go in for a much complex network called Integrated Extended SCADA System in 2008. By then, Karnataka also had EMS SCADA Network in ULDC Scheme of Power Grid Corporation of India Ltd, at 400 and 220 kV Levels only with about 112 Nodes. Following were the constraints:1) None of the above requirements of NE Policy 2003, could have been fulfilled with the available SCADA System,2) The Network was not collecting data from the balance 1265 Sub Stations3) Implementing Intra State ABT was jeopardised, even though Inter State ABT Worked,4) There was no mechanism for ESCOMs to monitor and control their consumption,5) Energy Loss calculations were hay way,6) None of the EMS functions could be run for want of data from remaining stations,7) There was no Training Simulator to educate despatchers,8) OAC mechanism was not automatic,9) There were serious limitations in the Data Base, which prevented Utilities in SouthernRegion to add incremental Sub Stations.Therefore, Karnataka had to Sun-Set the existing ULDC Network and established a mostversatile Network called “Integrated Extended Scada” Project” (IES) for a total of 1377Nodes, which ultimately became the biggest Network in the World in 2008.For this, 16 Control Centres were established as follows:1) One Main Hub having both EMS and DMS2) A Disastrous Recovery Hub, 25 kms away from Main Hub, having both EMS & DMS3) 5 Control Centres for Distribution Companies,4) 6 Control Centres for Transmission Zones,5) A separate Control Centre for Bangalore City Distribution Automation System,Notable features of the Network are:1) The Complete Network operates with MFTDMA VSATs2) 10 MBPs OFC Links are used for ICCP in addition to SCPC VSAT Links3) ESCOMs monitor their own Grid4) The Network has 31 Remote Man Machine Interfaces for Management Functions,5) All latest EMS and DMS Functions are operational,6) The Inter-State and Intra State ABT are fully operational,7) The Services are SCADA Data, IP Data, Speech, Facsimile and Video Conferencing,8) The Energy Billing and Energy Audit for all the Companies are automated,9) OAC mechanism is fully automated,10) The Network has a Real Time Simulator also,11) Further to implementing this Network, about 25 Sub Stations are unmanned.
机译:据分析,印度的大多数SCADA网络都不完整。因此,论文中仍然保留了智能电网这种方法。如果某些公用事业公司的EMS SCADA系统电压为400 kV和220 kV,则其他公用事业公司的DMS SCADA系统的电压为33 kV和11 kV。除了卡纳塔克邦以外,印度没有其他国家。卡纳塔克邦拥有从11 kV到400 kV的完整SCADA网络。我曾是卡纳塔克邦网络的架构师,在世界各地被人们称为“卡纳塔克邦模型”。 2003年的印度国家电力政策(National Electricity Policy 2003(India))提出了公用事业网络中的一些重要要求,这些改革是诸如将公用事业捆绑到发电,输电和配电领域的改革之类的: 1.适应开放访问系统, 2.实时向Open Access客户(OAC)和公用事业提供线路流, 3.使电力公司的活动透明化4.将ABT运营类型扩展到ESCOM 5.为ESCOM创建单独的负载调度中心,以管理自己的网格, 6.为变速箱操作员创建单独的负荷发送中心 7.使所有电压等级下的能量损耗计算更加自动化, 这使卡纳塔克邦在2008年加入了一个称为集成扩展SCADA系统的复杂得多的网络。那时,卡纳塔克邦还拥有印度电网公司的ULDC方案中的EMS SCADA网络,其400和220 kV级别仅具有约112个节点。以下是限制条件: 1)现有的SCADA系统无法满足NE Policy 2003的上述要求, 2)网络未从剩余的1265个子站中收集数据 3)即使州际ABT奏效,实施州内ABT的工作也受到威胁, 4)ESCOM没有监视和控制其消费的机制, 5)能量损失的计算方法很复杂, 6)如果缺少剩余站的数据,则无法运行任何EMS功能, 7)没有用于培训调度员的培训模拟器, 8)OAC机制不是自动的, 9)数据库存在严重局限性,阻止了南部地区的公用事业 添加增量子站的区域。 因此,卡纳塔克邦必须通过Sun-Set现有的ULDC网络并建立一个 多功能网络,称为“集成扩展Scada”项目(IES),总计1377 节点最终在2008年成为世界上最大的网络。 为此,建立了16个控制中心,具体如下: 1)一个同时具有EMS和DMS的主集线器 2)一个灾难恢复中心,距离主要中心25公里,具有EMS和DMS 3)5个配电公司控制中心, 4)6个传输区控制中心, 5)班加罗尔城市配电自动化系统的单独控制中心, 该网络的显着特点是: 1)完整网络与MFTDMA VSAT一起运行 2)除SCPC VSAT链接外,ICCP还使用10 MBP的OFC链接 3)ESCOM监视自己的网格 4)网络具有31个用于管理功能的远程人机界面, 5)所有最新的EMS和DMS功能都可以运行, 6)州际和州内ABT全面运作, 7)服务包括SCADA数据,IP数据,语音,传真和视频会议, 8)所有公司的能源账单和能源审计都是自动化的, 9)OAC机制是完全自动化的, 10)网络也有一个实时模拟器, 11)除了实施该网络外,还约有25个子站无人值守。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号