The Veterans Memorial Bridge linking Weirton, West Virginia and Steubenville, Ohio is an asymmetricalcable-stayed structure with a single tower. Main span lengths are 820 feet and 688 feet. The bridgeaccommodates six lanes of traffic on a 92-foot wide deck. Due to the asymmetrical arrangementsignificant uplift forces are induced at the end of the shorter span. These forces were originallytransferred through bolted steel tie-downs into large concrete counter weights integral with theabutment. The bridge was opened to traffic in May of 1990. The fracture critical tie-down assembliesshowed signs of distress due to fatigue failure of some of their anchor bolts and needed replacementafter only 14 years of service. This paper explains the causes of the poor performance of the initial tiedownsand discusses design and construction of the replacement systems. Installation of a redundantdual tie-down system that employs strand cables and inverted bearings was successfully completed inApril of 2009.
机译:连接西弗吉尼亚州威顿市和俄亥俄州斯托本维尔的退伍军人纪念桥是不对称的 单塔斜拉结构。主跨长度为820英尺和688英尺。桥 在92英尺宽的甲板上可容纳6条车道。由于不对称的安排 在较短跨度的末端会产生很大的升力。这些力量原本是 通过螺栓连接的钢架将其转移到与混凝土一体的大型混凝土配重中 邻接。这座桥于1990年5月通车。 由于某些地脚螺栓疲劳失效而显示困扰的迹象,需要更换 服务仅14年。本文解释了最初的绑架表现不佳的原因 并讨论了替换系统的设计和建造。安装冗余 采用绞合电缆和倒置轴承的双束缚系统已于2007年成功完成 2009年4月。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号