首页> 外文会议>Conseil International des Grands Reseaux Electriques;International Council on Large Electric Systems;CIGRE session >Commissioning Test on the 1000 kV UHV AC Demonstration Project and Operation Monitoring of the Main Equipments
【24h】

Commissioning Test on the 1000 kV UHV AC Demonstration Project and Operation Monitoring of the Main Equipments

机译:1000 kV特高压交流示范工程调试测试及主要设备运行监控

获取原文

摘要

The 1000 kV Jindongnan-Nanyang-Jingmen UHV AC demonstration project developed byState Grid Corporation of China is the first UHV project in the country. The successfulconstruction of this project is of great significance to the reliability of China’s electric powersupply, and to the research and application of UHV transmission technology around theworld. This paper has provided an overview of the commissioning test, including the researchand determination of commissioning plan, testing results, and the evaluation to operationstatus of main equipments.Commissioning test is the initial work before putting the project into the commercialoperation. To guarantee the success of the tests, State Grid has started the research andpreparation at the beginning of the construction. The final system test has been confirmedbased on a large amount of calculation and optimization, including 15 experiments of threedifferent types.Voltage-raising experiments have been conducted to test the insulation of UHV equipments,to verify the polarity of CVT and CT, and to check the accuracy of relay protections. Suchexperiments should be taken in small isolated systems due to the requirement for the safety ofequipments and systems. When taking experiments on the 1000 kV UHV AC transmissionsystem, it is necessary to avoid generators' self-excitation phenomenon, otherwise it woulddamage power equipments due to the higher over-voltage. Meanwhile, there are several 500kV substations from generating units to UHV substations. The safety of Central and NorthChina power grids must be maintained once the bus bar of any 500 kV station is isolated fromthe nominal system.The experiments on equipments switching have been conducted to test the capability of UHVcircuit breakers and switching of electrical equipments, to check protective actions, and tomeasure the switching over-voltage. There are four test items confirmed eventually with the switching UHV no-load transformer, the switching no-load transmission line and low-voltagecompensating equipments.The 1000 kV UHV AC TL is the connecting line between North and Central China powergrids, with a gross installed capacity of over 3 million kVA. The network experiments areconducted to obtain the system operating characteristics and control rules, and to verify thevalidity of control strategies and simulations.Since the project is put into operation, it has realized a dual function, full voltage, and largetransmission capacity. It has withstood severe weather conditions such as thunderstorm,heavy wind, high temperature, frigid, etc, and has successfully undertaken a series of testsincluding annual examinations, as well as heavy transmission load in both summer andwinter. The system of this project has been operated stably, and all the equipments have beenworking smoothly. The technical and economical efficiency and reliability of equipmentshave been further approved. With the aim to maintain a timely and accurately commandoperation condition of equipments, a condition monitoring system for UHV substations andmain equipments of transmission lines has been developed. And the configuration principle,the functional composition, and the equipment operation condition of this conditionmonitoring system are also introduced in this paper.The successful construction of UHV AC demonstration project in China symbolizes the majorbreakthrough in key technology and equipments of the UHV AC system, which is of greatsignificance to the reliability of China’s electric power supply, and the research andapplication of UHV transmission technology around the world.
机译:美国国家电力公司开发的1000 kV金东南—南阳—荆门特高压交流示范项目 中国国家电网公司是该国第一个特高压项目。成功的 该项目的建设对中国电力的可靠性具有重要意义 供应,并为周围地区特高压输电技术的研究和应用 世界。本文提供了调试测试的概述,包括研究 并确定调试计划,测试结果以及对运行的评估 主要设备的状态。 调试测试是将项目投入商业之前的初步工作 手术。为了保证测试的成功,国家电网已开始研究并 施工开始时的准备工作。最终系统测试已确认 基于大量的计算和优化,包括三个实验的15个 不同种类。 已经进行了升压实验以测试特高压设备的绝缘, 验证CVT和CT的极性,并检查继电保护的准确性。这样的 由于对安全性的要求,应在小型隔离系统中进行实验 设备和系统。在进行1000 kV特高压交流输电的实验时 系统,必须避免发电机的自激现象,否则会 过高的电压会损坏电力设备。同时,有几百个 从发电机组到特高压变电站的kV变电站。中部和北部的安全 一旦任何500 kV站的母线与 名义系统。 已经进行了设备切换实验以测试特高压的能力 断路器和电气设备的开关,以检查保护措施并 测量开关过电压。最终通过开关超高压空载变压器,开关空载传输线和低压确定了四个测试项目 补偿设备。 1000 kV特高压交流TL是华北和华中电力之间的连接线 电网,总装机容量超过300万千伏安。网络实验是 进行以获取系统的运行特性和控制规则,并验证 控制策略和模拟的有效性。 该项目自投产以来,已实现了双重功能,全电压,大体积。 传输能力。它经受住了恶劣的天气条件,例如雷暴, 强风,高温,严寒等,并已成功进行了一系列测试 包括年度检查,以及夏季和夏季的繁重传输负荷 冬天。本项目系统运行稳定,所有设备均已完工。 工作顺利。设备的技术经济效率和可靠性 已得到进一步批准。目的是保持及时准确的指挥 设备的运行状态,特高压变电站的状态监控系统以及 输电线路主要设备研制成功。以及配置原理, 该条件的功能组成和设备操作条件 本文还介绍了监控系统。 中国特高压交流示范项目的成功建设标志着重大 特高压交流系统关键技术和装备取得重大突破 对中国电力供应可靠性的重要性以及研究和 特高压输电技术在世界范围内的应用。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号