THE CONTROL TECHNIQUE OF NACHAOKOU BRIDGE IN XIAMEN OF CHINA

机译:厦门那阔口大桥的控制技术。

获取原文

摘要

In this paper, the key technologies of construction control of X-type steel box tied arch bridge constructed by full framing are discussed in detail with the Nachaokou Bridge in Xiamen City in China as engineering background. Firstly, simulation the interaction of pile foundation、 tie-bar and arch rib in construction process .Secondly, effect of longitudinal gradient is taken into account in simulation calculation of tensioning force of the tie members. Thirdly, the effects of braces deformation and temperature change on assembling location of arch rib were put on much emphasis. Finally, Pre-jacking transverse brace and optimizing procedure of tensioning tie bar is discussed.
机译:本文以厦门市那巢口大桥为工程背景,详细讨论了全框架构筑的X型钢箱式拱桥施工控制的关键技术。首先模拟了桩基,拉杆和拱肋在施工过程中的相互作用。其次,在模拟计算拉杆构件拉力时,考虑了纵向坡度的影响。第三,着重强调了支架变形和温度变化对拱肋装配位置的影响。最后,讨论了顶举式横撑和张紧拉杆的优化过程。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号