Regulatory uncertainty and its effects on monitoring activities of a major demonstration project: The Illinois Basin-Decatur Project case

机译:监管不确定性及其对重大示范项目监测活动的影响:伊利诺伊州盆地 - 癸丹项目案件

获取原文

摘要

Regulatory uncertainty is a component of carbon storage projects that can significantly affect project resources and timelines. The Illinois Basin-Decatur Project (1BDP) is a one-million tonne, deep-saline CO2 storage project led by the Midwest Geologic Sequestration Consortium (MGSC) that was initiated before the United States carbon storage regulatory framework was fully developed. To address uncertainty in the evolving regulatory environment, a comprehensive, risk-based, monitoring strategy was used that was expected to be over and above the anticipated new regulatory requirements. Ten years after its initiation, the IBDP has successfully completed the pre-injection and injection phases and is currently in the post-injection site care and monitoring phase. The IBDP experienced two lengthy permitting processes that proved to be the rate-limiting factor for the project, increased the length of time before the project could begin injection, and required additional resources to conduct the project. Future projects are likely to continue to have significant amounts of regulatory uncertainty as their respective project designs and monitoring programs will need to be evaluated by regulators on a case-by-case basis. Operators and regulators alike can benefit from frequent proactive communications during the permitting process in order to significantly reduce the length of the permitting process, maintain the critical safeguards of the Class VI rules, and ultimately meet timely goals for reductions to atmospheric CO2 emissions.
机译:监管不确定性是碳储存项目的组成部分,可以显着影响项目资源和时间表。伊利诺伊州盆地 - 解放项目(1BDP)是一百万吨,深盐水二氧化碳储存项目,由中西部地质封存联盟(MGSC)领导,在美国碳储存监管框架完全开发之前启动。为了解决不断变化的监管环境中的不确定性,使用全面,风险的监测策略,预计将超过预期的新监管要求。启动后十年后,IBDP已成功完成预注射和注射阶段,目前在注射后现场护理和监测阶段。 IBDP经历了两种冗长的允许流程,被证明是项目的速率限制因素,在项目开始注入之前增加了时间的时间长度,以及所需的额外资源进行项目。未来的项目可能会继续具有大量的监管不确定性,因为他们各自的项目设计和监测计划需要根据案例的规定评估。运营商和监管机构在许可过程中可以从经常主动通信中受益,以便大大减少允许流程的长度,维护VI规则的关键保障,并最终满足及时降低到大气二氧化碳排放的目标。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号