COMPACTION GROUTING FOR SINKHOLE REPAIR AT WAC BENNETT DAM

机译:WAC BENNETT DAM的打孔修补压实灌浆

获取原文

摘要

WAC Bennett dam is a zoned earth embankment slightly greater than 600 ft (183 m) in height. Two sinkholes, of which the deepest descended about 400 ft (120 m) from the crest, were discovered in the core of the dam in 1996. Compaction Grouting was chosen as the best remedial method, and was used. Because even the slightest chance of hydraulic fracturing of the core could not be tolerated, grouting was carefully designed and controlled including: precision drilling of the deep holes to within a verticality tolerance of one degree; continuous analytical evaluation of the grouting based on real time computer monitoring; careful control of the grout mix and especially its aggregate component; and, rigid control of the grout injection rate. The dam core was also monitored during grouting using a broad range of instrumentation, both on and within the embankment. Procedures were verified by a full-scale test before working on the dam.
机译:WAC Bennett大坝是一个带状的土堤,高度略大于600英尺(183 m)。在1996年的大坝中部发现了两个汇水坑,其中最深的汇水距坝顶下降了400英尺(120 m)。选择压实灌浆作为最佳补救方法,并加以使用。由于甚至不能容忍岩心发生水力压裂的最小机会,因此对注浆进行了精心设计和控制,其中包括:在深孔内精确钻孔,垂直度公差在1度以内;基于实时计算机监控的灌浆连续分析评估;仔细控制灌浆混合物,尤其是其骨料成分;严格控制灌浆速度。在灌浆过程中,还使用路堤内部和内部的各种仪器对坝心进行了监测。在大坝上工作之前,已通过全面测试对程序进行了验证。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号