This paper discusses the planning and execution of the URSA topisdes module and drilling rig installation and the integration of hull, topsides deck and rig systems. This work included module and rig transportation and setting, topsides structural integration, Tension Leg Platform (TLP) safety, utilities and process facilities bookup and systems commisiioning. TShe original execution plans called for a Gulf of Mexico Misissippi Canyon (MC-809) on-site module setting onto a tendoned hull and and hook-up to the modules after hull tendon istallation. The four-month delay of the TLP project installaton from Jue 1998 to October 1998 necessitated a radical change in execution plans if the original first oil trgets were to have a chance of being met. In March 1998, the decision was made to set the mdoules and perform a partial integration at a nearshore site in Curacao, the Netherlands Antilles. The TLP hull would then make a manned 25+ day tow to the Gulf of Mexico for tendon installation, followed by completion of the TLP production facilities hook-up an commissioning.
机译:本文讨论了URSA topisdes模块的计划和执行以及钻机的安装以及船体,顶侧甲板和钻机系统的集成。这项工作包括模块和钻机的运输和安装,上部结构集成,张力腿平台(TLP)安全,公用事业和加工设施预订以及系统调试。最初的执行计划要求将墨西哥湾密西西比峡谷(MC-809)现场模块安装在带腱的船体上,并在船体腱固定后连接到这些模块。从1998年6月到1998年10月,TLP项目的安装推迟了四个月,如果要满足最初的第一批石油装备的要求,就必须对执行计划进行根本性的改变。 1998年3月,决定在安的列斯群岛库拉索岛的近岸站点安装模型并进行部分整合。然后,TLP船体将载人25天以上的拖船拖到墨西哥湾进行肌腱安装,然后完成TLP生产设施的连接调试。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号