History and Expansion of the panama Canal

机译:巴拿马运河的历史和扩建

获取原文

摘要

The widening of the Panama Canal to approximately 40 m (130 ft) for its entire length began just a few years ago. The original expansion program was slated for completion in 18 to 20 years, but has recently been reduced for completion within the next four years. This means that a tremendous amount of blasting at simultaneous points along the canal, by both the Panama Canal Commission (PCC) and many subcontractors, is necessary to achieve the new completion deadline. The accelerated program also imposed many logistical concerns, since marine traffic is always heavy and cannot be stopped for blasting. Because some of the large and heavy cargo vessels clear the bottom of the canal by only about 2 m (6 ft), the blasting cannot result in any large boulders into the center of the canal, for fear of grounding and damaging a vessel not to mention the traffic delays and lost income of approximately 1 to 2 million dollars per day.
机译:巴拿马运河的扩建全长约40 m(130 ft),始于几年前。最初的扩展计划原定于18到20年内完成,但最近被缩减以在未来四年内完成。这意味着巴拿马运河委员会(PCC)和许多分包商都必须在运河沿线的多个地点同时进行爆破,以达到新的完工期限。加速的计划还带来了许多后勤方面的问题,因为海上交通总是很繁忙,无法停下来进行爆破。由于一些大型和重型货船仅在距运河底部约2 m(6 ft)的距离内进行爆破,因此担心由于接地和损坏船体而导致爆破不会导致任何大石块进入运河中心。提到每天约有1-2百万美元的交通延误和收入损失。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号