首页> 外文会议>International symposium on reviewing the safety of existing nuclear power plants; 19961008-11; Vienna(AT) >SAFETY REVIEW FOLLOWING INSIGHTS INTO A MAJOR EVENT AT BAERSEBAECK 2 A Swedish example-course of action
【24h】

SAFETY REVIEW FOLLOWING INSIGHTS INTO A MAJOR EVENT AT BAERSEBAECK 2 A Swedish example-course of action

机译:安全审查之后,对BAERSEBAECK 2的一项重大事件进行了了解

获取原文
获取原文并翻译 | 示例

摘要

When Baersebaeck 2 was restarted after the annual outage on 28 July 1992, a safety relief valve opened inadvertently at less than 2% power and 3.0 MPa reactor pressure. This was caused by a leaking pilot valve which had been assembled incorrectly. The leaking pilot valve caused depressurization of the main valve, which then opened. When the main valve opened, the reactor pressure acted on the rupture disc in this valve. When the reactor pressure reached 3 MPa, the rupture disc broke and a jet of steam was released into the containment. The containment was isolated and the containment vessel spray system (CVSS) and the emergency core cooling system were automatically started. The steam jet caused mineral insulation material to be dislodged from the pipes situated close to the safety relief valve. Insulation material was flying about in the containment. The amount of dislodged insulation material was about 200 kg; approximately 100 kg of this material was flushed down into the condensation pool by steam flow and by water flow from the CVSS. This incident did not jeopardize the safety of the plant, but further investigation and remediation were required because of the potential of the incident. In order to restore the safety of nuclear plants with a similar design, five of the Swedish plants were forced by the Swedish Nuclear Power Inspectorate (SKI) to shut down. The conditions for resuming plant operation were that temporary modifications should be made and that the safety function analysis in probabilistic terms should be shown to be equivalent to the original safety analysis. Four of the plants were able to restart approximately six months after the event. At Oskarshamn 1, other safety deficiencies were found during the outage; these required a longer outage period in order to restore the level of safety commonly assumed to be necessary at that time. In the modification and control project for Oskarshamn 1, called FENIX, the first step, FENIX Restart, aimed at performing the modifications required to obtain permission for continuation of plant operation. In order to meet long term demands for safety, the FENIX project also initiated a modernization programme, plans for which had been made in parallel with the implementation of the FENIX Restart programme. This modernization will be performed in several steps during the yearly outages in the period 1996-1999. The deficiencies found at Oskarshamn 1 forced the utility to perform a much larger inspection, control and modification programme than had initially been anticipated. SKI requested that, before restart of the plant, a complementary safety report should be submitted to it, with an overall evaluation of plant safety. Plant modifications made at Barseback 2 within the FENIX project are described in the paper. When the FENIX project reached its major milestone-restart of Oskarshamn 1, it had demonstrated that the plant was in a better state than had been evaluated in 1992, before the event at Barseback. However,
机译:1992年7月28日,Baersebaeck 2在年度停电后重新启动时,安全泄压阀在功率不足2%和反应堆压力为3.0 MPa的情况下意外打开。这是由于先导阀泄漏而造成的,该先导阀的组装不正确。先导阀泄漏导致主阀减压,然后将其打开。当主阀打开时,反应堆压力作用在该阀的破裂盘上。当反应堆压力达到3 MPa时,破裂盘破裂,蒸汽束被释放到安全壳中。隔离了安全壳,并自动启动了安全壳喷淋系统(CVSS)和应急堆芯冷却系统。蒸汽喷射导致矿物绝缘材料从安全释放阀附近的管道中脱落。绝缘材料在安全壳内飞来飞去。绝缘材料的脱落量约为200千克;通过蒸汽和来自CVSS的水将大约100千克的这种材料冲入冷凝池。该事件并未危害工厂的安全,但由于该事件的可能性,需要进行进一步的调查和补救。为了恢复具有类似设计的核电厂的安全,瑞典核电监察局(SKI)迫使五家瑞典核电厂关闭。恢复工厂运行的条件是应进行临时​​修改,并以概率形式显示安全功能分析应与原始安全分析等效。事件发生后大约六个月,其中四家工厂能够重启。在Oskarshamn 1停运期间,还发现了其他安全缺陷。这些要求更长的中断时间,以恢复当时通常认为必需的安全级别。在名为FENIX的Oskarshamn 1的修改和控制项目中,第一步是FENIX Restart,旨在执行所需的修改,以获取继续运行工厂的许可。为了满足长期的安全需求,FENIX项目还启动了一项现代化计划,该计划是在实施FENIX Restart计划的同时制定的。在1996-1999年的年度停机期间,将分几步进行此现代化。 Oskarshamn 1站发现的缺陷迫使该公用事业公司执行比最初预期的要大得多的检查,控制和修改程序。 SKI要求在重新启动工厂之前,应向其提交补充安全报告,并对工厂安全进行总体评估。本文描述了在FENIX项目中Barseback 2进行的工厂修改。当FENIX项目达到Oskarshamn 1的主要里程碑重新启动时,这表明该工厂的状态比1992年Barseback事故发生之前评估的状态更好。然而,

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号