Stability Assessment of Baira Siul-Pong Transmission Line, Himachal Pradesh, India

机译:印度喜马al尔邦Baira Siul-Pong输电线路的稳定性评估

获取原文
获取原文并翻译 | 示例

摘要

The present study has clearly revealed that the location of most of the transmission towers had been arbitrarily selected without giving due consideration to topographical conditions for the foundation. At some locations no adequate slopes and drains have been provided to drain off the rainwater quickly from the tower foundation. At various towers puddle marks under the transmission tower legs were clearly visible indicating the accumulation of water during monsoon. Out of 126 tower locations surveyed in Baira Siul - Pong transmission line, 25 tower sites have been found to be located on unsafe zones - three towers located near the reservoir were found to be highly unstable, where as 22 other towers were categorized as unstable. Among these the slopes around 10 towers need immediate suitable control measures to strengthen the stability of the towers. The most vulnerable zone had been found near the reservoir where tower nos. 52, 53 and 56 were located. In fact, these towers needed realignment in view of the safety and commercial viability of the strategically located transmission line.
机译:本研究清楚地表明,大多数输电塔的位置是在没有适当考虑基础地形条件的情况下随意选择的。在某些位置,没有提供足够的坡度和排水沟以快速排出塔基础的雨水。在各个塔架上,输电塔腿下方的水坑痕迹清晰可见,表明季风期间积水。在Baira Siul-Pong输电线路中调查的126个塔位置中,发现25个塔位置位于不安全区域-位于水库附近的三座塔被发现高度不稳定,另外22座塔被归类为不稳定。其中10座塔附近的斜坡需要立即采取适当的控制措施,以增强塔的稳定性。在水库编号塔附近发现了最脆弱的区域。分别位于52、53和56。实际上,考虑到战略位置的传输线的安全性和商业可行性,这些塔需要重新调整。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号