首页> 外文会议>International Conference on Estuaries and Coasts(ICEC-2006); 20061128-30; Guangzhou(CN) >Ijmuiden breakwaters: selection of renovation options and scale model investigations for a new top layer of concrete blocks on the impermeable core
【24h】

Ijmuiden breakwaters: selection of renovation options and scale model investigations for a new top layer of concrete blocks on the impermeable core

机译:艾默伊登防波堤:防渗芯新顶层混凝土砌块的翻新方案选择和比例模型研究

获取原文
获取原文并翻译 | 示例

摘要

The Ijmuiden breakwaters need significant and increasing maintenance every year. Especially the top layer of concrete cubes suffers severe damage. These cubes, placed directly on a 2 m thick watertight stone asphalt layer, are not stable.Now, 50 years after construction, also the old cubes and asphalt are seriously degenerated. Just after construction it became clear that the original stone asphalt top layer was not stable due to high water pressures in the core, propagating through the open toe construction below the asphalt. The concrete cubes, placed on top, should give contra weight. It is clear that renovation is necessary in the near future. The Civil Engineering Division of the Dutch Ministry of Transport, Public Works and Water Management has completed a study on the possibilities of renovation of the breakwaters. Many different solutions have been compared: from complete reconstruction to the creation of openings in the impermeable asphalt layer. The most feasible solution seems to be the replacement of the concrete blocks by heavier blocks, eventually in combination with a fill layer of rock on the impermeable asphalt. It is expected that a fill layer increases the stability of the new blocks and enables accurate placing of the blocks despite the unequal surface of the asphalt layer. To investigate the influence of the impermeable asphalt layer on the stability of the new concrete blocks, different model tests have been executed with one or two layers of blocks, with or without a fill layer. Also the placing method is varied and the thickness of the fill layer has been changed. The paper presents the comparison and selection of different renovation options and the results of exploratory model tests compared with the actual design formulas.
机译:艾默伊登防波堤每年都需要大量维护,而且需要不断增加维护。特别是混凝土立方体的顶层遭受了严重的破坏。这些立方体直接放置在2 m厚的不透水的石质沥青层上,现在不稳定,现在,在施工50年后,旧的立方体和沥青也被严重退化了。刚施工完后,很明显原来的石沥青顶层由于岩心中的高水压而不稳定,并在沥青下面的露趾结构中传播。放在顶部的混凝土立方体应具有相对的重量。显然,在不久的将来需要翻新。荷兰运输,公共工程和水管理部的土木工程部完成了关于防波堤翻新可能性的研究。比较了许多不同的解决方案:从完全重建到在不渗透沥青层中创建开口。最可行的解决方案似乎是用较重的砖块代替混凝土砖块,最终与不透水沥青上的岩石填充层相结合。尽管沥青层的表面不相等,但预计填充层可提高新砌块的稳定性,并能够准确地放置砌块。为了研究不渗透性沥青层对新型混凝土砌块稳定性的影响,已对一层或两层砌块(有或没有填充层)进行了不同的模型测试。同样,放置方法也发生了变化,填充层的厚度也发生了变化。本文介绍了不同翻新方案的比较和选择,以及与实际设计公式相比较的探索性模型试验的结果。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号