Influence Analysis on a Subway Shield Tunnel Crossing below a High Speed Railway

机译:高速铁路下的地铁盾构隧道穿越影响分析

获取原文

摘要

This paper chooses the section between the stations of Majiapu Donglu and Yongdingmenwai Dajie on Beijing subway line 14 as the object. Numerical simulation is adopted to analyze the function of grouting reinforcement in control of deformation of the earth surface while a shield tunnel crosses below the Beijing-Tianjin intercity high speed railway. A 3D numerical model is made to simulate the construction process of a shield tunnel crossing below a high speed railway with a top speed of 350km/h, where the differential settlement between the two rails is required less than 5mm. The calculation result indicates that grouting reinforcement to the stratum of a certain extension of the crossing section can effectively control the settlement of the existing railway caused by shield tunneling so as to ensure safety operation of the railway. And the behindsegment grouting parameters and soil compartment pressure in the shield structure gained in the study can be instructional for further design and construction of tunnels.
机译:本文以北京地铁14号线马家堡东路站与永定门外大街之间的区间为对象。通过数值模拟,分析了盾构隧道穿越京津城际高速铁路下方时注浆加固在控制地表变形中的作用。建立了一个3D数值模型,以模拟最高时速为350km / h的高速铁路下方穿越盾构隧道的施工过程,其中两条轨道之间的差异沉降要求小于5mm。计算结果表明,对某交叉口某延伸段地层进行注浆加固可以有效控制盾构施工引起的既有铁路沉降,从而确保铁路的安全运行。研究中获得的盾构结构后段灌浆参数和土室压力可为隧道的进一步设计和施工提供指导。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号