Sizing a phase shifting transformer for congestion management in high wind generation areas

机译:调整相移变压器的尺寸以应对高风速发电厂的拥堵

获取原文

摘要

This paper presents a case study on sizing a phase shifting transformer to be located on a transmission line sensitive to overloading under N-1 network conditions. The line under analysis is a 220 kV line, which operates in parallel with a 400 kV line. This transmission line is located on the network section between Dobrogea, a peninsular area in the Romanian power system. The Dobrogea region is characterized by strong surplus of generation installed especially in wind power plants. During windy conditions, large amounts of power are transferred from Dobrogea either to the other areas of the Romanian power system or towards the Bulgarian power system. The aim is to identify the range of tap position of the phase shifting transformer for which neither the 220 kV line nor other transmission line will be overloaded under normal or N-1 operating conditions.
机译:本文提供了一个案例研究,该案例的目的是将移相变压器的尺寸设置为位于N-1网络条件下对过载敏感的传输线上。分析中的线路是220 kV线路,与400 kV线路并行运行。该传输线位于罗马尼亚电力系统中的半岛地区多布罗加(Dobrogea)之间的网络部分。多布罗加地区的特点是大量发电过剩,尤其是在风力发电厂中。在刮风的情况下,大量的电力从多布罗加转移到罗马尼亚电力系统的其他地区或保加利亚电力系统。目的是确定相移变压器的抽头位置范围,在正常或N-1操作条件下,对于该相移变压器,220 kV线路或其他传输线路均不会过载。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号