STUDY ON MULTI-MODE PROJECT SCHEDULING PROBLEM WITH FLEXIBLE RESOURCE-CONSTRAINT

机译:柔性资源约束的多模式项目调度问题研究

获取原文
获取原文并翻译 | 示例

摘要

All of the literatures dealt with RCPSP assume a completely rigid resource-constraint, which means the contractors schedule the projects only according to their self-owned resources. In fact the contractors would like to get additional resources if the earnings to do so exceeding corresponding cost. Namely, the resource-constraint is not completely rigid, but flexible in some degree. We put forward the multi mode project scheduling problem with flexible resource-constraint (MMPSP-FRC), analyze its relationship with other researches on PSP, select maximizing the project NPV as the objective, and formulate mathematic model of the problem. Finally, we give several recommendations for future research.
机译:有关RCPSP的所有文献均假设完全严格的资源约束,这意味着承包商仅根据其自有资源来计划项目。实际上,如果承包商的收入超过了相应的成本,他们希望获得更多的资源。即,资源约束不是完全严格的,而是一定程度的灵活。提出了具有弹性资源约束的多模式项目调度问题(MMPSP-FRC),分析了其与PSP其他研究的关系,选择最大化项目净现值为目标,建立了问题的数学模型。最后,我们提出了一些建议,供以后进行研究。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号